Town Operations Center
Overview |
News & Updates |
Key Values |
TOC-Related Agenda Items
The Town Operations Center, the largest capital project in Town government’s
history at $52 million, has been completed at Millhouse Road north
of Eubanks Road. Location Map The entire lot is 89 acres with the center
complex comprising four buildings occupying about 54 acres.
The facility houses the Public Works and Transportation departments,
which were required to vacate their former UNC-owned site along Martin Luther King Jr. Boulevard.
The Town held a groundbreaking ceremony on Oct. 29, 2004, construction was finished in Spring 2007, and Town departments moved into the facility in May and June of 2007.
The Town’s Percent for Art Ordinance set aside an estimated $420,000 for
public art. The Public Arts Commission selected Larry Kirkland as the artist
for the Town Operations Center. Kirkland is noted for his mastery and skill in
using engraved stone, cast bronze, glass, water and light. A graduate of Oregon State
University and the University of Kansas, Kirkland is a past recipient of a
Fellowship from the National Endowment for the Arts. He has created numerous
public artworks over the past 30 years and is currently designing a garden for
the Cranbrook Academy of Art in Michigan.
- 09/07/2007
- TOC Dedication and Grand Opening
- 08/03/2007
- Save the Date: Town Operations Center Dedication
- 06/29/2007
- Chapel Hill Transit Move
- 05/10/2007
- Historic Move to Town Operations Center Scheduled Friday
- 04/13/2007
- Town Operations Center Move Begins
- 10/23/2006
- Town Operations Center Update
- 05/12/2006
- Millhouse Road Construction
- 10/27/2005
-
Town to hold groundbreaking for Town Operations Center
- 10/21/2005
-
Millhouse Road Widening Project Begins
- 10/7/2004
-
Building Program And Overall Budget Revised In Response To Cost Estimates Based On The Detailed Design
- 07/16/2004
- Plans For The Buildings And The Site Layout Revised
- 02/29/2004
- Drawings From The Special Use Permit Application Refined
- 12/31/2003
- Application for Special Use Permit Prepared
- 11/30/2003
- Concept Plan Worked Into Design Drawings
- 10/31/2003
- Town Council Adopted Concept Plans And Preliminary Budgets For The Transportation And Public Works Portions
- 09/30/2003
- Town Council Considered A 15-Year Concept Plan And Preliminary Budget
- 08/31/2003
- Concept Plan And Preliminary Cost Projections Reviewed
- 06/30/2003
- Draft Conceptual Plan Reviewed By Advisory Boards
- 05/31/2003
- Design Workshop Held The Week Of May 19
- 04/30/2003
- Design Refined With The Addition Of Another 13 Acres
- 03/31/2003
- Town Council Reviewed Design Options From 2/17–2/21 Intensive Design Workshop
- 02/28/2003
- Town Council Completed Town Operations Center Design Advisory Committee Appointments
- 01/31/2003
- Town Council Approved A Process And Schedule For Development Of Conceptual Design And Cost Estimate
The project will reflect the Council’s key values of sustainability,
environmental sensitivity and fiscal prudence.
Sustainable Development
-
High Performance Guidelines – Triangle ‘J’ Council of Government
- Elements include Daylighting, Rainwater Collection, Photovoltaic
Systems, Solar Water Heating and Geothermal Mechanical System.
Environmental Sensitivity
- Environmental Sensitivity is reflected in the site design, which
minimizes clearing and impact on the site’s Resource Conservation Districts
(RCD’s).
- Stormwater Management is improved by utilizing pervious pavement, wet
ponds and bio-retention areas.
Fiscal Prudence
- Fiscal Prudence is promoted by the site-specific design, which minimizes
grading and balances earthwork. The bids received for the Early Sitework
Package verify this.
- Building program has been carefully scrutinized to minimize costs while
supporting operational needs and the project’s core values.
- 06/20/2005
Resolution Awarding a Bid for Construction of the Town Operations Center Off-Site Utility Improvements.
Resolution Awarding Bid for Construction of the Town Operations Center Off-Site Roadway Improvements.
Resolution Awarding a Bid for Construction of the Town Operations Center.
Delegation of Authority to Conduct Hearing on Bid Withdrawal.
Town Operations Center –Project Ordinance Amendments
- 06/15/2005
-
Resolution Calling a Special Meeting of the Town Council on June 20, 2005
- 05/23/2005
-
Rejection of the Bid for the Town Operations Center Off-Site Improvement Project
- 04/11/2005
-
Change Order to the Town Operations Center Site Work Contract
- 04/05/2005
-
Installment Financing Approval for the Town Operations Center
- 03/21/2005
-
Public Hearing on Installment Financing Contract for the Town Operations Center
- 02/28/2005
Presentation of Public Arts Projects.
Building Elevations.
Status of Work and Options for Council Consideration
- 10/27/2004
-
Update on the Town Operations Center Project
- 11/24/2003
Budget Ordinances for the Town Operations Center Capital Project
Municipal Agreement between the Town and the State for Millhouse Road Improvements
Contract with Corley Redfoot Zack, Inc. for Town Operations Center Design Work
Report on Potential Debt Service Costs of the Town Operations Center
- 11/17/2003
-
Concept Plan Review: Town Operations Center
- 10/27/2003
Introduction to Concept Plan and Preliminary Budget for Town Operations Center.
Public Works Operations
Transit Operations
Report on Possible Day Care Center at Town Operations Center
- 09/08/2003
Town Operations Center Request for Expedited Review
Town Operations Center Budget and Concept Plan
Consideration of Issues Related to a Potential Day Care Center at the Town Operations Center
- 06/23/2003
Bid Award for Installment Contract for Land Purchase
Town Operations Center Draft Conceptual Plan and Preliminary Cost Projections
- 06/09/2003
Proposed Purchase of Land for Town Operations Center Using Installment Financing
Extension of Consultant Contract for Town Operations Center
Options for Financing Public Improvements
- 05/12/2003
Budget Amendments for Town Operations Center Design
- 03/03/2003
Consideration of Preliminary Design Options for Town Operations Center
- 01/13/2003
Process for Preliminary Design and Cost Estimation for Town Operations Center
- 12/09/2002
Contract and Budget Amendment for Preliminary Design Services for Town Operations Center