ORANGE WATER AND SEWER AUTHORITY

 Quality Service Since 1977

 

 

Discussion Paper

 

Water and Sewer Capacity Implications of Increased Density in OWASA’s Carrboro-Chapel Hill Service Area

February 22, 2006

 

 

Executive Summary

 

OWASA can meet the utility needs of increased development density within the currently defined urban services area of Carrboro and Chapel Hill, but meeting those needs while maintaining the level of service expected by OWASA’s customers will require additional collaboration among OWASA, local governments, and the development community.

 

Highly efficient water conservation technologies are readily available that can support increased development density with little or no net increase in water service demands.  Many of these advanced efficiency measures can be implemented through existing legal authority and local review and approval procedures that are already in place, but some may require ordinance changes or new enabling legislation.  OWASA is ready and willing to provide technical assistance to Carrboro, Chapel Hill, and Orange County if they choose to move in this direction, and we will consider adopting water use efficiency standards for new development that will be served by OWASA. 

 

The ultimate capacity of OWASA’s water supply and wastewater treatment facilities are based on projections of future water and wastewater treatment demands that correspond to housing and employment levels that exceed Carrboro’s and Chapel Hill’s buildout projections by more than 20 percent.  We believe that this provides a conservative margin of safety for meeting the capacity needs of future development.

 

OWASA’s existing reservoir/quarry water supply system and its future expansion can meet the buildout needs of the Carrboro/Chapel Hill/University community, including a certain level of additional development density; however, our community will become more vulnerable to severe drought conditions beginning around 2015 and lasting until the Stone Quarry expansion is available for water storage in the mid-2030s.  The OWASA/UNC water reuse system, which will initially serve the University’s main campus, is an essential tool for reducing that future vulnerability.  Other measures include lowering projected water demands through conservation and improved efficiency, and/or by developing additional supply sources.  The primary goal of OWASA’s long-range conservation program is to reduce water shortage risks without having to rely on additional sources.

 

OWASA water sales and reservoir withdrawals for the past four years have remained below the historically high levels observed in 2001 and 2002.  This is likely due to a combination of weather factors, more conservative customer consumption, and the recycling of water treatment plant process water that was previously released to an intermittent creek.  Water withdrawals from University Lake and Cane Creek were 20 percent less in 2005 than projected in OWASA’s 2001 Master Plan.

 

Substantial reductions in summer peak demands at the Jones Ferry Road Water Treatment Plant indicate that customers are using less water for outdoor irrigation, perhaps in response to OWASA’s seasonal rate structure and to year-round conservation standards enacted by Carrboro, Chapel Hill, and Orange County.

 

Decreasing peak flows at the Mason Farm Wastewater Plant during rainy periods suggest that OWASA’s long-term program to systematically identify, repair and replace older sewer lines may be successfully reducing unwanted inflow and infiltration of stormwater into the sewer system.

 

If these recent trends continue, lower peak demands will delay the need for costly future expansions at both the water and wastewater treatment plants.

 

Despite significant reductions in overall consumption, the relative water demands of major customer classes have remained virtually unchanged and are nearly identical to those reported in the 2001 Master Plan: Single Family Residential (31%), Multi-Family Residential (24%), University (28%), and Commercial/Other (16%).

 

the effects of increased development densities on wastewater treatment capacity are more complex than effects on the water system.  Treatment capacity is affected by both the volume and quality of wastewater flow.  the total maximum daily load (TMDL) restrictions for nitrogen and phosphorus that will be established by Jordan Lake rules that the North Carolina Environmental Management Commission is expected to consider later this year may ultimately limit the amount of development that can be accommodated in the Carrboro-Chapel Hill urban services area.

 

Introduction and Background

 

On October 24, 2005, the Chapel Hill Town Council requested that OWASA provide a briefing about the effects of potential increases in allowable development density on OWASA’s ability to meet future water supply and wastewater treatment demands.  Copies of Council member Jim Ward’s petition and the Town Manager’s letter to OWASA are included as Attachments A and B.

 

This Discussion Paper provides background for that briefing, which is scheduled for February 27, 2006.  The paper will also support presentations to the Orange County Board of Commissioners and Carrboro Board of Aldermen on March 2 and March 14, 2006, respectively.

 

Purpose and Scope

 

Purpose:  To provide information and generate discussion among local elected officials and staff, OWASA Board members, interested citizens, and the development community about OWASA’s water and wastewater capacity and our ability to meet future demands if higher development densities are allowed.  Topics include:

 

Scope:  This report focuses primarily on issues related to residential, commercial, and downtown development in Carrboro and Chapel Hill.  It does not address increased development density per se associated with UNC’s main campus or Carolina North development, although projections for these facilities have been factored into all demand forecasts presented here.  OWASA continues to work closely with the University in supporting on-campus infrastructure needs – including water conservation and reuse strategies for both the main campus and Carolina North – and has incorporated the most up to date University information available in our estimates of long-term water supply and wastewater treatment demands for the OWASA system. 

 

The Question: Can OWASA continue to meet our community’s water and wastewater service needs if development densities are allowed to increase beyond the levels currently permitted by local comprehensive plans and zoning ordinances?

 

The Short Answer is Yes – To a Degree:  We can and will meet the utility needs of increased development density within the defined urban services area of Carrboro and Chapel Hill, but achieving this while still maintaining the level of service desired by OWASA’s customers will require additional and continued collaboration among OWASA, local governments, and the development community.  A more complete answer is provided below.

 

Long-Term Adequacy of OWASA’s Water Supply

 

An overview of historic and projected water demands, current and future supply capacities, and potential deficits is provided in Figure 1 and explained below.

 

The intersection of the diagonal demand lines in Figure 1 with the horizontal capacity lines represent periods when anticipated demand will equal or exceed the estimated safe yield of the reservoir/quarry system.  This does not mean that we will run out of water at that time; but, the system will only be able to provide the indicated amount of water if the 30-year or 2002 drought-of-record should recur.  On the basis of nearly 80 years of hydrologic records, the probability that 30-year drought conditions will not occur in any given year is 29 out of 30, or nearly 97 percent.  In other words, there is a 97 percent chance that the reservoir/quarry system will produce more than the specified safe yield in any given year.  The probability of exceeding the record drought yield (which is less than the 30-year yield) is even greater.

 

The probability of depleting OWASA’s reservoir/quarry system under various conditions of supply and demand is illustrated in Figures 2, 3, and 4.  These figures also provide graphic guidelines for determining when to invoke different levels of OWASA’s water conservation standards. 

 

Figures 3 and 4 illustrate the relative risks and conservation guidelines of the current reservoir/quarry system under demand conditions of 10 mgd and 11 mgd.

 

 

 

 

 

 

Figures 1 through 4 indicate that our community will become more vulnerable to severe drought conditions, especially beginning around 2015 until the expanded Stone Quarry is available for water storage sometime in the mid-2030s.  We can lessen that vulnerability by reducing projected water demands and/or by developing additional water supply sources.  The primary goal of OWASA’s conservation and demand management program, as adopted by the Board of Directors in April 2005, is to reduce water shortage risks without having to rely on water from additional sources. Suggestions about how this might be achieved through increased water use efficiency, especially in new development, are discussed later in this report.

 

 

 

How Does OWASA Estimate Future Demands for Water and Wastewater Service?

 

Future demand projections are generated from currently available information about plans for major new development activities (such as UNC’s main campus and Carolina North), changes in local building trends, recent water consumption data and trends, reuse projections from the University, and assumptions about future water conservation among all customer classes.  A list of key assumptions and information sources on which OWASA’s most current projections are based is presented in Attachment C.  Wastewater demand projections are generated by applying an empirically derived factor of 0.923 to corresponding drinking water demand projections, reflecting the fact that only a portion of the drinking water used in the community is returned as wastewater.  A spreadsheet with detailed calculations and results is available on request.

 

Long-term demand forecasts extend through 2050, when we assume that build-out will have occurred; i.e., forecasts for 2050 represent OWASA’s best guess at “ultimate” capacity needs.  We recognize that Carrboro’s and Chapel Hill’s projections of future population and employment, as reflected in Transportation Analysis Zone (TAZ) data, do not extend beyond 2030 or 2035, and that both towns expect to be substantially built out by then.  OWASA’s projections of future water and wastewater treatment demands therefore correspond to housing and employment levels that exceed Carrboro’s and Chapel Hill’s buildout projections by more than 20 percent.  We believe that this provides a conservative margin of safety for meeting the capacity needs of future development.

 

We also recognize that the actual pace and timing of growth in the community and the University may result in short-term departures from our projected demand trends, but such departures are not expected to affect long-term estimates of water and sewer system capacity needs.  As more detailed growth plans are developed by Carrboro, Chapel Hill, and UNC, OWASA will continue to revise and refine our projected demands accordingly.  We expect, for example, that the more or less linear pattern assumed for future growth (as depicted in Figure 1), will likely bend upward in the middle years before leveling off at or below projected buildout levels.

 

Are There Any Options for Additional Water Supply Sources That Could Reduce Our Vulnerability to Severe Droughts Before the Expanded Stone Quarry Is Available in the 2030s?

 

OWASA’s 5 percent allocation of the Jordan Lake water supply storage capacity will yield an average of about 5 mgd. If used by our community, this  could substantially reduce our vulnerability to severe droughts until the expanded Quarry Reservoir is available in the 2030s.  However, constructing facilities to obtain and transport water from Jordan Lake to OWASA’s water treatment plant in Carrboro would cost approximately $45 million in today’s (2006) dollars – an expensive investment for a relatively small amount of additional capacity that OWASA would no longer need after the expanded quarry is developed.

 

A more viable scenario might be to obtain supplemental water through a partnership with neighboring utilities, such as Durham, Cary, or Chatham County, who already have developed – or plan to develop –  water supply facilities at Jordan Lake.  One option would be for OWASA to buy in to the construction or expansion of facilities could jointly serve two or more entities.  We would then receive treated water directly through our existing interconnection with Durham.  contractual agreements could be appropriately structured to guarantee a desired amount of water under specified terms.  (Any such agreements would be subject to local approval per the Water and Sewer Management, Planning and Boundary Agreement to which OWASA is a party along with the Towns of Carrboro, Chapel Hill, Hillsborough, and Orange County.)  A special study is currently underway through the UNC Water Resources Research Institute’s Urban Water Consortium to analyze the overall treatment, transmission, and interconnection capacities needed for OWASA, Durham, and Cary to meet their long-term demands with supplemental water from Jordan Lake.  The study will also outline a range of potential terms and agreements that might accomplish that goal.

 

Conservation, Demand Management, and Improved Water Efficiency

 

In April 2005 OWASA’s Board of Directors adopted a Goal and Objectives for OWASA’s Long-Term Water Conservation and Demand Management Program.  For the first time, this policy identifies conservation as a key element of our overall water supply planning process and commits to the creation of a long-term conservation and demand management program.  Highlights of the policy include:

 

Overall Goal:  “To develop, fund, and implement a cost-effective water conservation and demand management program that will meet our community’s long-term water supply needs (through 2050) by making the highest and best use of our local water resources and eliminating the need for costly new water supply sources and facilities.”

 

For Water Supply Sources:  “To assure that annual average day raw water demand does not exceed the reliable capacity of OWASA’s existing and planned supply sources (Cane Creek Reservoir, University Lake, and the Stone Quarry Reservoir), where “reliable capacity” is the estimated yield of the system under extended periods of low streamflow conditions, such as those that recur approximately once every 30 years, or under more extreme conditions, such as those of the 2001-2002 “drought of record.”

 

For Treatment, Storage, and Distribution Facilities:  “To manage peak day treated water demands in ways that will allow the deferral of major capital projects, such as expansion of the Jones Ferry Road Water Treatment Plant and associated finished water pumping and storage facilities.”

 

A key objective is to pursue conservation measures that are acceptable to and cost-effective for current and future customers.

 

Improved Water Use Efficiency Is Part of the Answer

 

With effective planning, existing water conservation technologies can support increased development densities with little or no net increase in water service demands.  By reducing expected water use by 25 percent, a given volume of water can accommodate 33 percent more units, where a “unit” may be a dwelling unit, plumbing fixture, square foot of developed area – or any other unit to which a rate of water use can be assigned.  Let’s assume, for example, that each unit of a 50-unit multi-family residential project uses 100 gallons of water per day (gpd), for a total of 5,000 gpd.  If water use is reduced by 25 percent (to 75 gpd per unit), the same 5,000 gallons of water can support a total of 67 units rather than just 50, representing a “density increase” of 33 percent with no net increase in the projected water needs.  Greater or lesser improvements in water efficiency could accommodate greater or lesser density increases.

 

Such efficiency improvements (conservation) are achievable through existing and readily available technologies.  If desired, many of these can be implemented through development review and approval procedures that already exist locally.  Examples include:

 

Many of these and other water efficiency measures can be implemented through existing Town and County review and approval procedures – both at the administrative and policy level – without the need for local ordinance changes or new enabling legislation.  OWASA is ready and willing to provide technical assistance to the Towns and County if they choose to move in this direction.  Additionally, we will consider the feasibility of adopting “water use efficiency standards of service” for new developments that will be served by OWASA.

 

 

Does Conservation and Improved Efficiency Save Capacity at the Wastewater Plant?

 

the effects of increased development densities on wastewater treatment capacity are more complex than on the water system.  wastewater plant capacity is substantially affected by both the volume of flow (which is mostly water) and the strength or amount of the waste contained in that flow.  Using water more efficiently through practices such as those outlined above can help reduce the volume of wastewater, but the amount of pollutants in the untreated sewage that must be treated will remain the same.  Waste loads (the actual amount of pollutants) will generally increase with increased development density. 

 

OWASA addresses wastewater treatment and capacity issues through the selection of specific processes or combinations of processes needed to produce a high quality effluent (treated wastewater released to the environment) that meets applicable environmental and water reuse standards.  Those decisions are made in the context of capital improvement projects needed to periodically increase treatment capacity and/or to respond to new or anticipated regulatory requirements.  The estimated buildout capacity and future plans for OWASA’s Mason Farm Wastewater Treatment Plant are based on our best projections of future flow, wastewater strength, and regulatory requirements. Long-term plans for the wastewater plant will continue to evolve as treatment technology evolves and as other assumptions change or become better defined.   

 

Although increased development density may increase the amount of waste that OWASA must ultimately treat, it is unlikely that this will affect total capacity or future treatment plant decisions as significantly as new or more stringent regulatory requirements, such as the total maximum daily load (TMDL) restrictions for nitrogen and phosphorus that will be set forth in Jordan Lake rules that the North Carolina Environmental Management Commission is expected to consider later this year.

 

Pipes in the Ground

 

OWASA’s overall water and sewer infrastructure – the pipes in the ground – is adequate to accommodate reasonable increases in development density. 

 

The water distribution system (pumps, pipes, and storage tanks) is generally designed to meet fire flow requirements that are substantially higher than everyday needs.  The wastewater collection system, with a minimum pipe diameter of eight inches, is able to accommodate flows from most foreseeable residential or commercial development.  The capacity of downstream sewer outfalls and interceptors is reviewed systematically through capital improvements projects such as those underway or about to begin in the Morgan Creek and Upper Bolin Creek sewer subbasins.  These evaluations rely extensively on existing or proposed land use, zoning, and density scenarios to estimate the capacity needs of downstream sewers. 

 

As with other components of the OWASA system, our water distribution and wastewater collection needs are reviewed and updated as new requirements or revised information, such as anticipated development density, become available. 

 

Recent and Anticipated Development Trends

 

The planning staffs of Carrboro, Chapel Hill, and OWASA recently convened to discuss local development trends, water and sewer utility implications, and information issues related to growth and buildout forecasts for OWASA’s Carrboro-Chapel Hill service area.   Staff participants were in general consensus on the following:

Recent Trends in OWASA Water and Sewer Demands

Summary

 

A combination of factors and trends support the conclusion that OWASA can meet the utility needs of increased development density within the currently defined urban services area of Carrboro and Chapel Hill.

 

The ultimate capacity of OWASA’s water supply and wastewater treatment facilities are based on projections of future water and wastewater treatment demands that correspond to housing and employment levels that exceed Carrboro’s and Chapel Hill’s buildout projections by more than 20 percent.  This provides a conservative margin of safety for meeting the capacity needs of future development.  Recently declining trends in water consumption, as well as the shift toward smaller residential lot sizes and more townhouse/multi-family construction with lower demands per unit for water and wastewater service, may offer additional margins of safety.

 

The existing reservoir/quarry water supply system and its future expansion can meet the buildout needs of the Carrboro/Chapel Hill/University community, including a certain level of additional development density; however, our community will become more vulnerable to severe drought conditions beginning around 2015 until the Stone Quarry expansion is available for water storage in the mid-2030s.  This vulnerability can be lessened by reducing projected water demands – especially through such essential programs as the OWASA/UNC reuse project – and/or by developing additional supply sources.  However, the primary goal of OWASA’s long-range conservation program is to reduce water shortage risks without having to rely on additional sources.

 

the effects of increased development densities on wastewater treatment capacity are more complex than effects on the water system.  Wastewater treatment capacity is affected by both the volume and quality of wastewater flow.  the total maximum daily load (TMDL) restrictions for nitrogen and phosphorus that will be set forth in Jordan Lake rules that the North Carolina Environmental Management Commission is expected to consider later this year may ultimately limit the amount of development that can be accommodated in the Carrboro-Chapel Hill urban services area.

 

Meeting the needs of additional density while still maintaining the level of service desired by OWASA’s customers will require additional and ongoing collaboration among OWASA, local governments, and the development community. 

 

                                                           

                                   

                                                                                                                                                                                    _______________________________________________________________________________________________________________________________________________________________________________________________________________________

                                                                        Edward A. Holland, AICP

                                                                        Planning Director

 

ATTACHMENTS

  1. Comprehensive Plan
  2. Briefing Request
  3. Water Demand Projections