A RESOLUTION APPROVING A REQUEST FOR AN EXTENSION OF THE COMPLETION DATE FOR THE YMCA (2006-05-08/R-7a)
Whereas, T. J. Land has requested an extension of the completion time limit for the YMCA; and
WHEREAS, Section 4.5.5(c)(2) of the Chapel Hill Land Use Management Ordinance requires that Council make the determination that a) the permit holder submitted the request within sixty (60) days of the completion date; b) the permit holder has proceeded with due diligence and good faith; and c) conditions have not changed so substantially as to warrant Town Council reconsideration of the approved development; and
WHEREAS, the Council has determined that a) the permit holder submitted the request within sixty (60) days of the completion date; b) the permit holder has proceeded with due diligence and good faith; and c) conditions have not changed so substantially as to warrant Town Council reconsideration of the approved development;
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Council approves the request by T. J. Land for the extension of the completion date of the YMCA to April 10, 2011, to allow construction of the project in accordance with the approved April 10, 2000 Special Use Permit Modification.
This the 8th day of May, 2006.