ATTACHMENT 4
Resolution
A
(Preliminary
Staff Recommendation)
A RESOLUTION APPROVING AN
APPLICATION FOR A PRELIMINARY PLAT FOR FAIRWAY HILL SUBDIVISION (File No.
9798-67-4341)
BE IT RESOLVED by the Council of the
Town of Chapel Hill that it finds that the Fairway Hill Subdivision, proposed
by H. E. Rayfield, Jr., on the property identified as Orange County Property
Identification Number 9798-67-4341, if developed according to the preliminary
site plan dated March 8, 2006 and revised July 20, 2006, and the conditions
listed below, would comply with the provisions of the Land Use Management
Ordinance:
These findings are based on the
following:
Stipulation Specific to the Development
- Expiration
of Preliminary Plat: That this Preliminary Plat approval shall be valid
for one year from the date of approval subject to reapproval by the Town
Manager in accordance with the provisions of the Land Use Management Ordinance.
- Number
of Lots: That this approval shall authorize the creation of 4
single-family lots on 5.1 acres.
Stipulations Related to Transportation, Access, and Circulation
- On-site
Road Improvements: That a 27-foot wide road, measured from back of curb to
back of curb, with 30-inch wide curb and gutter, within a 45-foot wide
right-of-way shall be built to Town Standard.
- Sidewalk
Improvements: That a 5-foot wide sidewalk shall be built to Town Standard
on one side of the new road and shall extend around the cul-de-sac.
- New Road Location: That the new subdivision roadway be located at
the northern portion of the site.
- Pavement
Marking Plan: That the applicant submits a signage and pavement marking
plan to be approved by the Town Manager prior to issuance of a Zoning
Compliance Permit. The signs and pavement markings shall be installed by the
applicant prior to issuance of the first Certificate of Occupancy for a
structure on the new lots.
- Pedestrian/Bicycle
Path to Aquabella Property: That the applicant or Homeowners’ Association
shall construct a 5-foot wide pervious surface improved public pedestrian/bicycle
path, to the Aquabella property. That the preferred location of the path shall
be between lots 3 and 4, or at an alternate location as determined by the Town
Manager. The design and location of the path shall be connected with the proposed
development of the adjacent residential development (also known as Aquabella
Subdivision). That the construction of the path involve minimal land
disturbance. As best as can be determined the final location of the path, and
design of the path, shall be approved by the Town Manager prior to issuance of
a Zoning Compliance Permit.
- Pedestrian/Bicycle
Path to Meadowmont Soccer Field: That prior to issuance of the first
Certificate of Occupancy, the applicant or Homeowners’ Association shall
construct a 5-foot wide pervious surface improved public pedestrian/bicycle
path to the Meadowmont Soccer Field. That the preferred location shall be
generally between lots 2 and 3. That the construction of the path shall
involve minimal land disturbance. That the final location and design of the
path shall be approved by the Town Manager prior to issuance of a Zoning
Compliance Permit.
- Pedestrian/Bicycle
Path Maintenance and Ownership: That the applicant or Homeowners’Association
shall be responsible for the construction and maintenance of the
public pedestrian/bicycle paths and installation and maintenance of signage.
That prior to the issuance of a Zoning Compliance Permit the applicant shall
provide for the Town Manager review and approval, a deed conveying to the
Homeowners’ Association, a 10-foot wide strip of land that contains the public
pedestrian/bicycle paths. The deed shall note that the Homeowners’ Association
is responsible for the maintenance of the pedestrian paths and associated
signage. That a copy of the approved recorded deeds shall be cross referenced
on the final plat at the Orange County Register of Deeds Office.
- Pedestrian/Bicycle Path
Easement: That with the recordation of a final plat, the applicant shall
dedicate to the Town, a 10-foot wide public pedestrian/bicycle easement on the
Homeowners’ Association property for the paths to the Aquabella Subdivision and
the Meadowmont soccer field. The easement and boundaries shall be reviewed and
approved by the Town Manager prior to recordation at the Orange County Register
of Deeds Office.
- Pedestrian/Bicycle Path
Signage: That prior to the issuance of the first building permit, or upon
completion of the grading of the subdivision street, the applicant or
Homeowners’ Association shall post signs at the general location of the two
proposed pedestrian/bicycle path stating “Location of Future Public
Pedestrian/Bicycle Path. The design and location of the sign shall be reviewed
and approved by the Town Manager prior to issuance of a Zoning Compliance
Permit. That upon completion of each path, the applicant or Homeowners’Association
shall post signs at the entrance of the path stating “Access to
Pedestrian/Bicycle Path”.
Stipulation Related to Recreation
- Payment-in-Lieu for
Required Recreation Area: That the applicant shall provide a
payment-in-lieu for that portion of the recreation area not satisfied by the
square footage associated with the two pedestrian/bicycle paths. The payment
amount shall be reviewed and approved by the Town Manager in accordance with
the Land Use Management Ordinance, Section 5.5.2. That the square footage
associated with the two proposed 5-foot wide pedestrian/bicycle paths shall be
considered suitable recreation area and counted toward reducing the required
payment-in-lieu. That the recreation payment amount shall be submitted to the
Town prior to recordation of the final plat.
- On-site Recreation Area:That the square footage associated with the two proposed 5-foot wide
pedestrian/bicycle paths shall be considered suitable recreation area as
defined by the Land Use Management Ordinance and counted toward reducing the
required payment-in-lieu.
Stipulations Related to Landscaping
- Landscape Buffer and
Planting Plan: That the applicant shall provide a 20-foot wide Type-C
buffer along the Country Club and Meadowmont soccer field property lines. A
landscaping planting plan for the bufferyard shall be reviewed and approved by
the Town Manager prior to the issuance of a Zoning Compliance Permit.
- Alternative Landscape
Buffer: That in lieu of providing a 20-foot Type “C” buffer at the Country
Club property line, an alternate buffer may provided between the proposed
development and the Chapel Hill Country Club. That an alternate landscape
buffer along the Chapel Hill Country Club property shall be reviewed and
approved by the Community Design Commission prior to the issuance of a Zoning
Compliance Permit.
- Landscape Bufferyard
Maintenance and Ownership: That prior to the recordation of the final plat
the applicant shall provide, for Town Manager review and approval, a deed
conveying to the Homeowners’ Association the area associated with the landscape
bufferyard. The deed shall note that the landscape bufferyard, is owned,
controlled and maintained by the Homeowners’ Association. The deed shall be
recorded concurrently with and cross-referenced on the recorded plat.
- Landscape Protection Plan:That a detailed Landscape Protection Plan, clearly indicating which rare and
specimen trees will be removed and preserved and indicating significant tree
stands, and including Town standard landscaping protection notes, shall be
approved by the Town Manager prior to issuance of a Zoning Compliance Permit.
- Tree Protection Fencing:That the limits of land disturbance and tree protection areas be indicated with
tree protection fencing and shown on the Landscape Protection Plan, to be
approved by the Town Manager prior to issuance of a Zoning Compliance Permit.
- Preservation of
Significant Trees: That the final plans and all applicable Single Family
Zoning Compliance Permits include the preservation of all trees identified in
the significant tree stand.
Stipulations Related to Resource Conservation District
- Boundaries: That the
boundaries of the Resource Conservation District be indicated on the final plat
and plan. A note shall be added to all final plats and final plans,
indicating, “Development shall be restricted within the Resource Conservation
District in accordance with the Chapel Hill Land Use Management Ordinance.”
- Construction Standards:That for encroachment(s) into the Resource Conservation District, the
requirements and standards of Section 3.6.3(g) of the Land Use Management
Ordinance, including minimization of land disturbance, and all other applicable
Resource Conservation District regulations must be adhered to. This approval
authorizes construction of a public roadway through the Resource Conservation
District.
- Variances: That all
variances necessary for development within the Resource Conservation District
are obtained before application for final plat or final plan approval for the
subject phase(s) of development. That no lot be created that would require a
Resource Conservation District Variance in order to be built upon.
- Buildable Lots: That
all residential construction, including clearing, grading and construction
shall be located entirely outside of the Resource Conservation District. That
prior to the issuance of a Zoning Compliance Permit, it must be demonstrated,
for each lot, that there is sufficient buildable area outside: the Resource
Conservation District; significant tree stands; slopes of 25 percent or
greater; easements; and building setback limits.
Stipulations Related To Stormwater Management
- Land Disturbance Activity
Prohibited in the Resource Conservation District: That all required
erosion control sediment basins and all stormwater improvements, including
associated clearing and grading, shall be located entirely outside of the
Resource Conservation District and shall not impact the root systems of any
significant trees.
- Stormwater Facility
Prohibited in the Public Right-of-Way: That all detention/retention
basins, stormwater facilities and associated infrastructure be located outside
of existing or proposed right-of-way as well as outside of all building
setbacks.
- Stormwater Management
Plan: That prior to the issuance of a Zoning Compliance Permit, the
applicant shall submit a Stormwater Management Plan for review and approval by
the Town Manager. The plan shall be based on the 1-year, 2-year, and 25-year
frequency, 24-hour duration storms, where the post-development stormwater
run-off rate shall not exceed the pre-development rate. The plan shall provide
for the retention of stormwater run-off volume for the 2-year storm. Engineered
stormwater facilities shall also remove 85 percent total suspended solids and
treat the first inch of precipitation utilizing NC Division of Water Quality
design standards.
- Best Management Practices:That the applicant shall employ Best Management Practices, such as drainage
swales and level spreaders, to manage the rate and quality of runoff, based on
best available information from the NC State University Cooperative Extension.
Bio-retention areas to be designed in accordance with the standards specified
in the Engineering Design Manual and the Land Use Management Ordinance. Final
design and locations shall be approved by the Town Manager prior to the
issuance of a Zoning Compliance Permit.
- Storm Drainageway
Easement: That all stormwater management improvements, outside public
right-of-way, shall be located inside reserved storm drainageway easements and
shown on the final plans and final plat, per Town guidelines, to be approved by
the Town Manager prior to the issuance of a Zoning Compliance Permit
- Stormwater Operations and
Maintenance Plan: That the applicant shall provide a Stormwater Operations
and Maintenance Plan for all engineered stormwater facilities. The plan shall include
the owner’s financial responsibility and include the maintenance schedule of
the facilities to ensure that it continues to function as originally intended
and shall be approved by the Town Manager, prior to the issuance of a Zoning
Compliance Permit. The Stormwater Operations and Maintenance Plan shall be
referenced in the Homeowners’ Association documents.
- Residential Stormwater
Impact Statement: That for each lot, a stormwater impact statement
addressing stormwater management on a lot by lot basis, must be reviewed and
approved by the Town Manager prior to the issuance of a Single Family Zoning
Compliance Permit for said lot. Residential stormwater facilities on individual
lots must be within a stormwater drainage easement and outside of the building
setbacks. Covenants shall be provided for the maintenance of the facilities.
A note to this effect shall be placed on the final plans and final plat.
- Erosion Control: That
a detailed soil erosion and sedimentation control plan, including provision for
maintenance of facilities and modifications of the plan if necessary, be
approved by the Orange County Erosion Control Officer and the Town Manager
prior to issuance of a Zoning Compliance Permit. That a performance guarantee
be provided in accordance with Section 5-97.1 of the Town Code of Ordinances
prior to issuance of any permit to begin land-disturbing activity.
- Silt Control: That
the applicant takes appropriate measures to prevent and remove the deposit of
wet or dry silt on adjacent paved roadways.
Stipulations Related to Steep Slopes
- That all Final Plan applications, including the Single-Family Zoning Compliance
Permits, shall demonstrate compliance with the steep slopes regulations in the
Land Use Management Ordinance. The application shall include a plan showing
residential building areas and street segments on slopes of 10 percent or
more. The plan shall indicating how the development and construction will
comply with the steep slopes regulations in the Land Use Management Ordinance
including:
- for
slopes of 10 – 15 percent, site preparation techniques shall be used which
minimize grading and site disturbance;
- for
slopes of 15 – 25 percent, demonstrate specialized site design techniques and
approaches for building and site preparation; and
- for
slopes of 25percent or greater, provide a detailed site analysis of soil
conditions, hydrology, bedrock conditions, and other engineering or
environmental aspects of the site.
Prior to the issuance of a Zoning Compliance Permit the Town Manager shall approve a
steep slope plan. Steep slope restrictions shall be referenced in the
Homeowners’ Association documents.
Stipulations Related to Water, Sewer, and Other Utilities
- Utility/Lighting Plan
Approval: That the final Utility/Lighting Plan be approved by Duke Energy,
Orange Water and Sewer Authority, BellSouth, Public Service Company, Time
Warner Cable, and the Town Manager prior to issuance of a Zoning Compliance
Permit.
- Street Lighting Plan:
That a street lighting plan shall be reviewed and approve by Duke
Energy and the Town Manager prior to the issuance of a Zoning Compliance
Permit. That if the proposed street lighting plan includes non-standard poles
and/or fixtures, that the plans and the Homeowners’ Association documents
indicate that the applicant, or Homeowners’ Association, shall be responsible
for the additional cost as determined by Duke Energy.
- OWASA Easements: That
easement documents as required by OWASA and the Town Manager be recorded
concurrently with the final plat. That the final plat shall be reviewed and
approved by OWASA and the Town Manager prior to the issuance of a Zoning
Compliance Permit.
- Placement of Utility
Lines Underground: That all new utility lines shall be placed underground.
- Fire Flow: That a
fire flow report shall be prepared and sealed by a registered professional engineer,
and shall show that flows meet the minimum requirements of the Town Design
Manual, to be approved by the Town Manager prior to issuance of a Zoning
Compliance Permit.
- Fire Hydrant Spacing:That maximum spacing between fire hydrants shall not exceed 400 feet, subject
to approval by the Town Manager.
Stipulations Related to Homeowners’ Association
- Homeowners’ Association:That a Homeowners’ Association be created that has the capacity to place a lien
on the property of a member who does not pay the annual charges for maintenance
of common areas, however designated. The Homeowners’ Association documents
shall be approved by the Town Manager prior to recordation at the Orange County
Register of Deeds Office and shall be cross-referenced on the final plat. The
Homeowners’ Association documents shall comply with Section 4.6.7 of the Land
Use Management Ordinance.
- Dedication of Common Area
to Homeowners’ Association: That the applicant provide for Town Manager
review and approval, a deed conveying to the Homeowners’ Association all common
and open space areas. These documents shall be reviewed and approved by the
Town Manager prior to recordation at the Orange County Register of Deeds Office
and cross-referenced on the final plat.
Miscellaneous Stipulations
- State or Federal
Approvals That any required State or federal permits or any required
encroachment agreements for development in areas such as wetlands must be
approved by the appropriate agencies and copies of the approved permits be
submitted to the Town Manager prior to the issuance of a Zoning Compliance
Permit.
- Street Names and
Addresses: That the name of the development and its streets and house
numbers be approved by the Town Manager prior to the issuance of a Zoning
Compliance Permit.
- Construction Management
Plan: That a Construction Management Plan, indicating how construction
vehicle and pedestrian traffic will be managed, shall be approved by the Town
Manager prior to the issuance of a Zoning Compliance Permit.
- Solid Waste Management
Plan: That a Solid Waste Management Plan, including provisions for
recycling, for managing and minimizing construction debris, and a
pre-demolition and pre-construction meeting, shall be approved by the Town
Manager prior to issuance of a Zoning Compliance Permit.
- Open Burning: That
the open burning of trees, limbs, stumps and construction debris association
with this development is prohibited.
- Detailed Plans: That
final detailed site plans, grading plans, utility/lighting plans, stormwater
management plans (with hydrologic calculations), and landscape plans and
landscape maintenance plans be approved by the Town Manager prior to issuance
of a Zoning Compliance Permit, and that such plans conform to the plans
approved by this application and demonstrate compliance with all applicable
conditions and the design standards of the Land Use Management Ordinance and
the Design Manual.
- As-Built Plans: That
as-built plans in DXF binary format using State plane coordinates, shall be
provided for street improvements and all other existing or proposed impervious
surfaces prior to issuance of the first Certificate of Occupancy.
- Plant Rescue: That
the applicant consider conducting plant rescue activities on the site prior to
initiation of development activity.
- Certificates of Occupancy:That no Certificates of Occupancy shall be issued until all required public
improvements are completed; and that a note to this effect shall be placed on
the final plat. That if the Town Manager approves a phasing plan, no
Certificates of Occupancy shall be issued for a phase until all required public
improvements for that phase are complete; no Building Permits for any phase
shall be issued until all public improvements required in previous phases are
completed to a point adjacent to the new phase, and that a note to this effect
shall be placed on the final plat.
- Construction Sign:That the applicant shall post a construction sign that lists the property
owner’s representative and telephone number, the contractor’s representative
and telephone number, and a telephone number for regulatory information at the
time of the commencement of any land disturbing activities. The construction
sign may have a maximum of 4 square feet of display area and may not exceed 6
feet in height. The sign shall be non-illuminated, and shall consist of light
letters on a dark background. That the Town Manager shall review and approve a
detail for the sign prior to the issuance of a Zoning Compliance Permit.
- Schools Adequate Public
Facilities Ordinance: That the applicant provides the necessary
Certificates of Adequacy of Public Schools prior to recordation of the final
plat.
- Continued Validity:That continued validity and effectiveness of this approval is expressly
conditioned on the continued compliance with the plans and conditions listed
above.
- Non-severability:That if any of the above conditions is held to be invalid, approval in its
entirety shall be void.
BE IT FURTHER RESOLVED by the Council
of the Town of Chapel Hill that the Council hereby approves the application for
a Preliminary Plat for the Fairway Hill Subdivision in accordance with the
plans and conditions listed above.
This the _____
day of _______________, 2006.