ATTACHMENT 1

 

 
Tentative Schedule for Moratorium and Northern Area Task Force Schedule

(assuming Task Force start May, 2007)

 

Key Steps

Time

Council Appoint Task Force

April 23, 2007

  • Council Public Hearing on Proposed moratorium and
  • Council Public Hearing to downzone University Station to Residential -1 District

May 7, 2007

Task Force (Tasks):

  • Review background information on transit oriented development, identification of transit corridors and Chapel Hill Long range transit Plan.
  • Develop a vision statement for the area.
  • Prepare recommendations for the Council’s consideration on development regulations, design standards and appearance guidelines for the implementation of transit oriented development along Martin Luther King Jr. Blvd, Weaver Dairy Road and Eubanks Road.
  • Develop recommendations on pedestrian and bicycle safety improvements throughout the study area. (Review of the NC86/Martin Luther King Jr. Blvd and Town-Wide Pedestrian Safety Evaluation Study.)

 

Task Force Proposals Drafted

May to September, 2007

Present Task Force Report to Town Council

Town Council Refer to Planning Board for Recommendation

October 8, 2007

Planning Board Recommendation

November, 2007

Council Public Hearing

As early as November 12, 2007

Council Action

As early as January, 2008