ATTACHMENT 3
LEED CRITERIA
Initial required LEED documentation for applicant’s seeking expedited
processing:
- Evidence that applicant’s design team includes a
registered member of the U.S Green Building Council;
- Evidence that the applicant has registered the project for
LEED Silver certification; and
- Evidence that the project team has started to prepare
documentation to satisfy LEED Silver certification prerequisite and credit
submittal requirements.
Continued required LEED documentation:
That in order to maintain expedited processing status, the applicant shall
submit evidence, during various stages of the Town’s review process,
documenting continued satisfactory progress towards achieving LEED Silver
certification.