PURPOSE
The purpose of this information item is to provide the Town Council with an
update on the status of staff efforts to examine and evaluate the EZ Rider
Division of Chapel Hill Transit.
BACKGROUND
Chapel Hill Transit provides Demand Response service throughout the towns of
Carrboro and Chapel Hill and the University of North Carolina. Demand Response
service consists of three services: Shared Ride, Feeder Service and EZ Rider.
The FY 07/08 operating budget is approximately $1.4 million and EZ Rider
service provides approximately 250 rides per day.
When I began as Transit Director my goal was to evaluate transit services to
ensure the town provides the highest level of service in the most cost
effective manner. First, we focused on improving the quality of service in the
fixed route system, including maintenance operations, service reliability,
staffing and policy evaluation.
During my budget presentation to the Council on February 28 2007, the
analysis of EZ Rider was identified as a primary activity for the 2007/08
fiscal year. This task would consist of several activities:
- Create an advisory committee of users, advocacy groups and potential
funding agencies to analyze rules, procedures and processes. Create a committee
of EZ Rider staff to do the same.
- Retain a consultant to analyze the operations of the demand response
system and recommend opportunities for system improvement.
- Investigate ways to work more collaboratively with other regional
providers and funding agencies with the goal of providing more effective
services and identifying possible funding sources in addition to the current Chapel Hill partners.
DISCUSSION
FY 2007/08 Budget Changes
We made several overtime management and staffing changes to allow EZ Rider
to operate more efficiently. After one quarter of operation this fiscal year,
these changes have had a positive budgetary impact, reducing the projected
annual expenditure for wages from $772,000 to approximately $690,000.
System Analysis
Eleven persons were selected to serve on the EZ Rider Advisory Committee, representing
various ages, ethnicity, disabilities and communities.
Below are the key concerns raised by the advisory committee and EZ Rider
staff:
EZ Rider Advisory Committee
- Poor service quality - long wait times for will calls, long travel
times, inability to schedule for times wanted
- Poor phone service - phones don’t work, cant get through on lines, poor
customer service from telephone attendants
- Scheduling - scheduling is poor, inefficient, non customer service focused.
EZ Rider Staff
- Scheduling is poor, need to revamp the scheduling process to become more
efficient, eliminate duplicating and overlapping trips.
- System capacity. The system is at capacity and drivers are challenged to
make trips and often run late.
- Rules and procedures. Chapel Hill Transit needs to improve the certification
process, implement rules on no shows, cancellations, etc. in order to better
control costs and make better use of driver time.
Short Term Improvements
The short term action steps listed below are designed to improve service,
better train personnel and deal with capacity issues.
- Reorganize staffing to return to pre-July 1 status.
- Evaluate phone operations and establish a performance monitoring system.
- Review scheduling practices to look at opportunities for grouping trips or
operating collaboratively to provide more efficient service, thereby improving
system capacity.
- Modify the ADA certification process to conform to Americans with
Disabilities guidelines as well as other regional transit operations to ensure
that all new customers meet ADA certification requirements.
- Review daily operations to implement any immediate improvements that can
be made in operations, dispatching or scheduling.
These short term actions steps can be implemented with in 30 days.
Long Term Activities
Over the next several months we will continue to engage the committees in a
review of system performance and to review operating policies and procedures as
follows.
- Develop and distribute an RFP for a consultant to evaluate EZ Rider
operations, services and policies for long term improvement.
- Investigate options to replace Strategen, our scheduling software.
- Purchase and install Mobile Data Terminals on all EZ Rider vehicles.
Budget Implications
Below is a summary of budgeted items.
- The FY 2007/08 budget included a recommendation to use State Maintenance
Assistance Funds to pay the consultant for our operations review.
- The cost to replace Strategen is not included in the budget. If a
further examination indicate that it is in the Town’s best interest to replace Strategen
it will be necessary to amend an existing capital grant or seek new funding to
purchase the new software.
- Mobile data terminals are included in a recent grant awarded by the
North Carolina DOT.