Table 1

Sidewalk Construction Projects Funded by General Obligation Bonds

 

2004-2008 Bond Funded Projects

 

 

 

Committed Projects

Construction By

Status

Committed funds

Curtis Road west side from Clayton Road to Elliott Road

Town Crews

Completed

$ 28,000

 Westminster Drive, north side each side of Banks Road

Town Crews

Completed

$ 25,000

Ransom Street, east side from McCauley to University Drive

Contractor

Completed

$ 75,000

Vance Street, south side Ransom Street to Pittsboro Street

Contractor

Completed

$ 39,500

Kenan Street, east side, Cameron Avenue to Franklin Street

Contractor

Completed

$ 61,500

Kingston Drive, east side, south from Weaver Dairy Road

Town Crews

Completed

$ 43,000

Estes Drive, south side from Franklin Street to Willow Drive ( no state funds available)

Contractor

Completed

$ 44,000

Culbreth Road both sides Channing Lane to US 15-501. Total cost estimate $87,000. $36,000 in STP DA funds will be refunded on completion

Contractor

Completed

$ 51,000

Fordham Boulevard, east side at northeast corner intersection with Estes Drive

Total cost $15,000. $12,000 in STP DA funds will be refunded on completion

Contractor

Completed

$ 3,000

Culbreth Road, south side, between Cobble Ridge Road and Rossburn Way.

Total cost estimate $113,000, $90,000 in STPDA funds will be refunded on completion funds

Contractor

Anticipated Start 2008-2009

$ 57,500

Martin Luther King Jr. Boulevard west side at Northfield Drive Total cost estimate $325,000. $260,000 in STP DA funds will be refunded on completion

Contractor

Completed

$15,000

North Street, north side, Martin Luther King Jr. Boulevard to Henderson Street

-

Pending

-

Hillsborough Street, south side, Bolinwood  Dr. to Martin Luther King Jr. Boulevard

Contractor

Completed

$129,000

Gomains Avenue, south side, from Craig Street to Bynum Street

Town Crews

Completed

$14,000

Sykes Street, east side, from Gomains Avenue to Whitaker Street

Town Crews

Completed

$23,800

Mitchell Lane, west side, from Lindsay Street to McDade/Roberson Street (CBDG funds were used)

Town Crews

Completed

$65,000 (total cost, see project below)

Mitchell Lane, west side, from McDade/Roberson Street to Caldwell Street (CBDG funds were used)

Town Crews

Completed

$65,000 (total cost, see project above)

Caldwell Street, south side, from Church Street to N. Columbia Street

Town Crews

Completed

$13,500

Pritchard Avenue Ext. & Longview Street, from Umstead Drive to N. Columbia Street

Contractor

Completed

$142,000

Sedgefield Drive from Weaver Dairy Road to Honeysuckle Road

Contractor

Completed

$63,000

Plant Road from E. Franklin Street to Community Center

Town Crews

Completed

$20,000

McMasters Street, south side, from Church Street to Edwards Street

Town Crews

Underway

$27,000

Kingston Drive, from Silver Cedar Lane approximately 200 feet north on the west side of Kingston Drive

Town Crews

Completed

$5,000

Ephesus Church Road, from Colony Woods to the Durham County Line

Contracted

Underway

$73,000

Estes Drive, from Burlage Circle to East Franklin Street

Contracted

Underway

$125,000