Roger, This email confirms our discussion this morning. ARE, the developer of
the IC, continues to be interested in developing the project even in these tough
financial times, and therefore as applicant, we request that you continue
the public hearing from 24 November 2008 to 26 January 2009. Thanks.
Bruce