Attachment C
Detailed Target Timeline for Town Review of CN Development Proposal
Date |
Action |
September 25 |
Council-Trustee work session (with public comment period): Presentation and discussion of development review process proposed by staff, Briefing and discussion of legal aspects of development agreements |
|
|
October 15 |
Regular Council meeting: Council discussion of review process |
October 22 |
Council-Trustee work session (with public comment periods): Discussion of detailed timeline and process for review; issues to be addressed |
October 31 |
University initiates process with written request for consideration new zone, map amendment, and development agreement; submits long-range plan, mid-term and early stage development plans; University submits background ecological studies and draft design guidelines |
|
|
November 3-17 |
Data collection on traffic counts for future traffic impact analysis; Town develops RFQ for consultants to conduct CN traffic impact analysis consistent with town guidelines and process |
November 10 |
Regular Council meeting: Council receives University’s Carolina North request and materials |
November 18 |
Council-Trustee work session (with public comment periods): Presentation and discussion of University-submitted plans and materials; discussion of process for addressing issues and categorization of issues |
November 19 |
Informational meeting for public and advisory boards (with staff report to Council/Trustees) – (1) Development review process, timing, opportunities for involvement, issues to be addressed; (2) Presentation and discussion of University’s October 31 submittals. {Additional staff updates provided to advisory boards at regularly scheduled meetings December through March.} |
|
|
December 3 |
Council-Trustee work session (with public comment periods): Discussion of scale of CN project to be addressed in initial development agreement, area to be rezoned, range and mix of uses in zone and development agreement |
December 8 |
Regular Council meeting: Staff update to Council on adequacy of town staff resources |
December 17 |
Interim fiscal impact analysis update presented to for staff review |
|
|
January 8 |
Joint University-Town staff briefing regarding formation of joint staff work teams for preparation of development agreement analysis and potential provisions. Joint staff work teams meet on Jan. 15, Jan. 22, Jan. 29, Feb. 5 |
January 10 |
Town Council work session: Update on Long Range Transit Plan; discussion of Carolina North issues |
January 12 |
Regular Council meeting: Council receives update on CN process |
January 14 |
Council-Trustee work session (with public comment periods): Presentations and discussion of housing, preservation of undisturbed areas |
January 22 |
Transportation Impact Analysis Request for Qualifications distributed |
January 29 |
Informational meeting for public and advisory boards (with staff report to Council/Trustees) – Presentation and discussion of rezoning, text amendment, and development agreement; presentation and discussion of proposed project, issues, and development review process, solicitation of ideas on metrics, standards, mitigation measures |
|
|
February 9 |
Regular Council meeting: Manager report on staff resources needed for project review |
February 9 |
Staff initial draft of LUMO text amendment and development agreement distributed to Council/Trustees |
February 11 |
Council-Trustee work session (with public comment periods): Presentation and discussion of transportation issues (parking, transit, roads, traffic) and stromwater utility; Update on on-going staff work |
February 19 |
Informational meeting for public and advisory boards (with staff report to Council/Trustees): |
February 27 |
Transportation Impact Analysis responses to RFQ due |
tba |
Final fiscal impact analysis report submitted by consultant |
|
|
March 2 |
Proposed text/map amendments, plan, and development agreement submitted to manager. Could be done in early April if additional discussion needed. |
March 4 |
Informational meeting for public and advisory boards (with staff report to Council/Trustees) |
tba |
Presentation to Council on fiscal impacts study |
March 9 |
Regular Council meeting: Council receives proposed ordinance amendments and development agreement; directs initiation of formal review. Could be done in early April if additional discussion needed. |
March 11 |
Council-Trustee work session (with public comment periods): Discussion fiscal impacts, energy generation, air quality, cumulative impacts, and sustainability; discussion of terms of development agreement. Additional March work session may be scheduled as needed |
|
|
April 1 |
Informational meeting for public and advisory boards (with staff report to Council/Trustees): Presentation and discussion of proposed plans and development agreement |
April 1-23 |
Advisory board meetings at regular meeting schedules |
April tba |
Transportation impact analysis submitted |
April 21 |
Planning board regular meeting: Planning Board discussion of proposed text and map amendments and proposed development agreement |
April 22 |
Council-Trustee work session (with public comment periods): Discussion of terms of development agreement. Additional April work session may be scheduled as needed. |
|
|
May 5 |
Planning board regular meeting: Planning Board recommendation on text/map amendments and development agreement |
May 11 |
Council regular public hearing: Public hearing on text/map amendments and development agreement |
May 21 |
Council-Trustee work session (with public comment periods): Discussion of terms of development agreement |
|
|
June 8 |
Regular Council meeting: Council deliberation |
June tba |
Additional public information meetings or hearings as needed |
June 22 |
Regular Council meeting: Council action text/map amendments and development agreement |
|
|
July 6 |
If approved, development agreement executed and recorded |