ATTACHMENT 2

 

Comparison of Adopted 2004-2010 Priority List,

Advisory Board Recommendations and

Manager’s Recommended 2006-2012 Priority List

 

Adopted 2004-2010 Chapel Hill Priority List

Transportation Board

Planning Board

Parks and Recreation Commission

Bicycle and Pedestrian Advisory Board

Greenways Commission

Manager’s Recommended 2006-2012 Priority List

1) Transit Capital

 

 

 

 

 

No change

2) Signal System Upgrade

Recommended as a priority.

 

 

 

 

 

No change

3) Estes Drive Extension

 

 

 

Request  immediate funding.

 

No change

4) Old Durham-Chapel Hill Road.

 

 

 

 

 

No change

5) Seawell School Road.

 

 

 

 

 

No change

6) Estes Drive, NC86 to Curtis

 

 

 

 

 

Reorder as priority #8.

7) Culbreth Road

 

 

 

 

 

Remove from priority list. Remaining portions of sidewalk along Culbreth Road to be provide through Town CIP.

8) Morgan Creek Greenway

 

Include as priority #5.

 

 

 

Reorder as priority #7. Project is partially funded from STP-DA.

9) Franklin St./Bolin Creek Geenway

 

 

 

 

 

Reorder as priority #10.

10) Estes Drive, Curtis to Fordham Blvd

 

 

 

 

 

Reorder as priority # 11.

11) Bolin Creek Greenway

Move to lower priority.

 

 

 

 

Reorder as priority # 12.

Adopted 2004-2010 Chapel Hill Priority List

Transportation Board

Planning Board

Parks and Recreation Commission

Bicycle and Pedestrian Advisory Board

Greenways Commission

Manager’s Recommended 2006-2012 Priority List

12) Pope Rd.-Ephesus Church Rd.

 

 

 

 

 

Reorder as priority # 15.

13)  Piney Mountain Road

Move to lower priority.

 

 

 

 

Reorder as priority # 16.

14) Mount Carmel Church Road

 

 

 

 

 

Reorder as priority # 17.

15) Dry Creek Greenway

 

 

 

 

 

Reorder as priority # 18.

16) Manning Drive, Bowles to Fordham Blvd

 

 

 

Questioned inclusion in Priority List.

 

Removed from priority list. Project would require additional right of way from environmentally sensitive area.

17)  Merritt Mill Road.

Recommended as priority.

 

 

 

 

Removed from list. Remaining portions of sidewalk to be provided through Town CIP.

18) Upper Booker Creek Greenway

 

 

 

 

 

Reorder as priority # 19.

19) County Club Road

 

 

 

 

 

Reorder as priority #20.

20) Fordham Boulevard

 

 

 

 

 

 

 

Reorder as priority # 21.

21)  Bolin Creek/Little Creek Greenway

 

 

 

 

 

Reorder as priority #22.

22) Old Mason Farm/Finley Golf Course Road

 

 

 

 

 

Project proposed as priority #23

NEW PROJECTS

 

 

 

 

 

 

Homestead Road.

Recommended

 

 

 

 

Included as priority #6.

NEW PROJECTS

Transportation Board

Planning Board

Parks and Recreation Commission

Bicycle and Pedestrian Advisory Board

Greenways Commission

Manager’s Recommended 2006-2012 Priority List

Community Center to Willow Drive Bicycle/ Pedestrian Connection

Recommended

 

 

 

 

Included as priority #9

Barbee Chapel Road

 

 

 

Recommended

 

Included as priority #13

Rail Trail

 

 

Recommended

 

Recommended

Included as priority #14