ATTACHMENT 4
OPTION 2 - South
side of the 400 block of
The western half of the south side of the 400 block is
proposed as Option 2. It extends 355 feet in length from the former Chrysler
dealership (419) west to the intersection with
The scope of work proposed includes installing the
underground utility ductbank and replacing the concrete curb, gutter, and
sidewalk. The concrete sidewalk would
extend across the two existing driveways to improve pedestrian safety.
Due to the location of existing raised brick planters in
the right-of-way at the face of the building at 419, we recommend that the
sidewalk width be narrowed in this area to approximately six feet and that the
narrower sidewalk width be continued another 120 feet. This will provide an opportunity to construct
new raised brick planters in the amenity strip between the sidewalk and the
curb. A total of 6 new street trees are
proposed to be added. Staff would work with the owners of adjacent
property to replace an existing split-rail fence with an ornamental iron fence
matching the fence proposed in the preliminary plan for the section of
Streetscape in front of 407 and
The estimated cost of construction for this project is $94,000,
including the 1% for public art.
Advantages of Option
2:
·
Would continue Streetscape improvements
completed by
·
Relatively lower pedestrian traffic would make
construction logistics easier.
Disadvantages of Option
2:
·
Existing right-of-way encroachments, such as
planters limit design solutions.