ATTACHMENT 1
TOWN OPERATIONS CENTER
PRELIMINARY BUDGET
October 27, 2003
Consistent with Ordinance – Corrected Dec. 19, 2003*
Public Works/Housing Transit TOTAL
Construction $18,352,546 $12,788,100 $31,140,646
Equipment 1,719,080 1,828,200 3,547,280
Subtotal (a) $20,071,626 $14,616,300 $34,687,926
Off-site (utilities, roads, signals) $ 1,648,500 $ 1,648,500 $ 3,297,000
Demolition 126,500 126,500 253,000
Subtotal (b) $21,846,626 $16,391,300 $38,237,926
10% Design, value engineering,
testing $ 2,184,662 $ 1,639,130 $ 3,823,792
Subtotal (c) $24,031,288 $18,030,430 $42,061,748
1% for Art $ 240,312 $ 180,304 $ 420,616
Subtotal (e) $24,271,600 $18,210,734 $42,482,334
Relocation expense $ 44,000 $ 13,000 $ 57,000
Removal underground tanks 75,400 96,000 171,400
Subtotal (f) $24,391,000 $18,319,734 $42,710,734
Contingency $ 215,793 $ 215,793
Subtotal (g) $18,535,527 $18,535,527
TOTALS $24,391,000 $18,535,527 $42,926,527
*Budget presented at the Town Council meeting on October 27, 2003 has been adjusted to incorporate additions made at that meeting, including the addition of $1,120,400 for Public Housing Maintenance (including 10% for design, value engineering and testing) and $25,775 for widening Millhouse Road from 30 ft. to 36 ft (including 10% for design, value engineering and testing, and 1% for art.); and to be consistent with the budget ordinances 2003-11-24/O-1 and -2 adopted November 24, 2003.