AGENDA #5c
MEMORANDUM
TO: Mayor and Town Council
FROM: W. Calvin Horton, Town Manager
SUBJECT: Report on Revised 2004-2005 Public Housing Operating Budget
DATE: January 10, 2005
INTRODUCTION
The purpose of this memorandum is to present information on a revised 2004-2005 operating budget for the public housing program. A revision to the 2004-2005 budget is necessary because of reduced subsidy from the U.S. Department of Housing and Urban Development (HUD) and increased public housing program costs.
BACKGROUND
In October 2004, we received notification from HUD that the amount of operating subsidy for 2004-2005 will be $1,109,767, which is $25,318 less than the $1,135,085 included in the original budget estimates. The notification from HUD also included an additional expense of $7,775 for resident participation activities.
The public housing program also has additional expenses totaling $32,000 ($18,000 County recycling fee and $14,000 Town stormwater management fee). When the 2004-2005 budget was approved by the Council, on March 1, 2004, the amount of these additional fees was not known.
With the reduction in income and increased costs, the 2004-2005 public housing operating budget has a revenue shortfall of about $65,000. The $65,000 shortfall results from the following:
Reduction in HUD subsidy $25,318
HUD addition of resident participation allocation $ 7,775
Addition of County recycling fee $18,000
Addition of Town storm water management fee $14,000
TOTAL $65,093
DISCUSSION
In order to balance the 2004-2005 public housing operating budget, expenditures must be reduced. Therefore, we have made the following budget reductions:
Reduced personnel due to vacant position, actual pay increases,
health insurance, and workman’s compensation $53,680
Reduced postage $ 4,000
Reduced travel $ 4,000
Reduced tenant activities $ 3,000
Eliminated purchase of 1 vehicle $17,000
TOTAL $81,680
Below is a summary of the revised 2004-2005 budget for the public housing program. We will take precautions to make sure that expenditures do not exceed revenues
Revised 2004-2005 Budget for the Public Housing Program
Original Ytd Exp Revised
2004-2005 2004-2005 2004-2005
Budget Actual Budget
Personnel Services 1,011,819 363,134 958,139
Operations 482,046 169,402 531,226
Non-Routine Maint. 84,520 10,943 90,799
Capital Outlay 75,300 905 63,478
Total 1,653,685 544,384 1,643,642
Estimated Rental Income 363,846 137,558 363,846
Estimated Federal Subsidy 1,135,085 414,697 1,109,767
Est. Fund Bal. to be Used 131,818 ------- 147,093
Other Income 22,936 13,886 22,936
Total 1,653,685 544,384 1,643,642
Est. Fund Bal. 6-30-05 329,399 ------- 314,124
HUD Recommended Fund 297,013 ------- 297,873
Balance
Based on the revised budget, we would use $147,093 of the fund balance to cover the expenditures. The remaining fund balance would be $314,124, which is $16,251 above HUD’S recommended amount of $297,873.