AGENDA #10
MEMORANDUM
TO: Mayor and Town Council
FROM: W. Calvin Horton, Town Manager
SUBJECT: Proposed Phasing Plan for Southern Community Park
DATE: April 11, 2005
The attached Resolution A would designate a first phase of development for the Southern Community Park.
Resolution B would authorize the Town Manager to amend the Southern Community Park’s Special Use Permit application to propose the construction of 60 additional parking spaces along the south side of Dogwood Acres Drive.
Resolution C would continue the Southern Community Park Special Use Permit review to May 9, 2005.
BACKGROUND
In 1986, and 1989, Chapel Hill voters approved Parks bonds, portions of which were used to purchase the Southern Community Park property. In 1997, and 2001, Orange County voters approved Parks bonds that included funds designated for the Southern Community Park.
In July 2000, the Council appointed the Southern Community Park Conceptual Plan Committee. On March 25, 2002, the Town Council adopted the Report of the Southern Community Park Conceptual Plan Committee and directed the Town Manager to prepare an implementation plan. The Orange County Board of Commissioners adopted the park Concept Plan on March 5, 2003.
Concept Plan reviews of the application were conducted by the Community Design Commission on June 16, 2004, and by the Town Council on June 21, 2004.
A Public Hearing was opened on February 21, 2005, and comments were received at that time. The Board of Orange County Commissioners reviewed the plans on March 15, 2005, and provided comments and questions.
On March 24, 2005, the Council/County Commission Project Planning Committee met and recommended that the phasing plan discussed below be pursued. The Committee also recommended that the Town’s Special Use Permit be amended to show 60 additional parking spaces on the south side of Dogwood Acres Drive.
DISCUSSION
BUDGET
To date we have spent or committed $332,000 for design and other pre-construction expenses. This leaves a budget of $2,510,000 for construction of the first phase of the project. This is at least $900,000 less than required if the entire program were to be built at one time.
SOURCES OF REVENUE
1997 Orange County Parks Bond $842,000
2002 Orange County Parks Bond 2,000,000
TOTAL REVENUE $2,842,000
PROPOSED EXPENDITURES
Pre-construction costs 1 $332,000
Construction 2,168,000
Contingency 2 342,000
TOTAL EXPENDITURES $2,842,000
1 This amount includes design, permitting costs, surveying, public art, OWASA tap fees, required studies, and soils exploration.
2 15% of construction budget.
PROPOSED PHASING PLAN
This project is likely to be completed in two or more phases. The first phase would consist of a portion of the program that could be accomplished within the existing construction budget of $2,168,000. A complete list of the facilities that are proposed in the current Special Use Permit application are listed in Attachment A. We believe that the following proposed first phase of park development would provide the best combination of facilities for the available funds.
Infrastructure Improvements: The proposed infrastructure improvements would ensure that all essential elements of the park development are brought to the site in the first phase. These include all utilities, pedestrian and bicycle trails and paths, stormwater facilities, and traffic calming needed to serve the site. A portion of the parking would be provided as would all landscaping adjacent to areas developed in phase one.
· Parking lot (south) with 65 or 125 spaces depending on the Council’s decision to possibly add 60 spaces onto the Dogwood Acres Drive parking lot
· All sewer and water extensions
· Restrooms
· Sidewalks
· Extension of Fan Branch Greenway Trail to the dog park
· Traffic calming
· Extensive landscape buffers along US 15-501
· Dry detention basins
· Constructed wetland basins
· Public art
Recreational Elements in Priority Order: The following list of recreation facilities would be provided in phase one. These are the facilities that we believe are most needed by the community based on input received during the public processes of the park development, the Parks and Recreation Master Plan, and day to day communications with the public. It is clear that the community’s greatest recreational need at this time is for additional athletic fields that can be used for soccer. Although the other facilities listed here, with exception of the disk golf course, can be found in other public parks in Chapel Hill there are currently no such public facilities south of Fordham Boulevard.
· Athletic/soccer fields (3) (This option would not include athletic lights. Lights would be added in a future phase although we would provide all conduits in this phase to make future installation easier)
· Children’s play area (1)
· Picnic Shelters (1 large, 1 small)
· Dog park
· Meadow/grass play area
· Disk golf course
Potential Benefits of this Proposed Phasing Plan
Potential Issues with this Proposed Phasing Plan
Elements that would not be included in this Proposed Phasing Plan: The following elements would not be constructed in the first phase:
· New street to connect US 15-501 to park and ride lot
· Parking lot (north) with 158 spaces
· Maintenance building
· Extension of Fan Branch Greenway Trail from the dog park to Merritt Drive
· Basketball courts (2)
· In line hockey court (1)
· Children’s splash park (1)
· Athletic/soccer field lights
· Youth ballfield
PROPOSAL TO INCREASE PARKING ALONG DOGWOOD ACRES DRIVE
The 65 spaces in the Dogwood Acres Drive parking lot would not likely be enough to handle the number of park users that would be expected during the soccer season. We would expect that park patrons would have to use the Southern Park and Ride lot and the Scroggs School parking lot unless other parking is constructed. During the late afternoon hours the park and ride lot would likely not have enough spaces for soccer games and practices.
An option would be to increase the number of parking spaces off of Dogwood Acres Drive by up to 60 spaces. Please see the attached sketch showing the proposed layout of the parking lot.
Potential Benefits of the Proposal to Add Parking Spaces off of Dogwood Acres Drive
Potential Issues with the Proposal to Add Parking Spaces along Dogwood Acres Drive
SUMMARY
We believe that the recommended phasing option would allow us to build the park elements most needed by the community and most often mentioned by citizens and elected officials throughout the public process. The recommended phasing plan would likely create some parking and maintenance issues that would not be addressed until funds for a second phase would become available.
The proposal to add additional parking spaces along Dogwood Acres Drive could resolve many of the parking problems anticipated with the recommended first phase. However, the proposal would add cost to the project, delay the Special Use Permit process, and would intrude somewhat into the western open space area that we have tried to protect in the design.
RECOMMENDATION
Project Planning Committee's Recommendation: The joint Town Council/County Commissioners Project Planning Committee unanimously recommended that the first phase of the Southern Community Park should include:
· A parking lot on the south side of Dogwood Acres Drive with a total of 125 spaces. (This includes 60 spaces more than is currently reflected on the Town’s Special Use Permit.)
· All sewer and water extensions, restrooms, sidewalks, traffic calming, landscape buffers along US 15-501, dry detention basins, and constructed wetland basins
· Public art
· Extension of Fan Branch Greenway Trail to the dog park
· Picnic Shelters (1 large, 1 small)
· Children’s play area (1)
· Three athletic/soccer fields without lights.
· Meadow/grass play area
· Dog park
· Disk golf course
This recommendation is the same as the Manager’s recommendation.
Manager's Recommendation: We recommend that the Council adopt the following resolutions:
ATTACHMENTS
RESOLUTION A
A RESOLUTION DESIGNATING A FIRST PHASE OF DEVELOPMENT FOR THE SOUTHERN COMMUNITY PARK (2005-04-11/R-9a)
WHEREAS, on February 21, 2005, the Council opened a public hearing to gather comments related to a Special Use Permit application for the Southern Community Park; and
WHEREAS, the estimated cost of the entire proposed park development is at least $900,000 more than budget;
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the first phase of development of the Southern Community Park shall consist of:
This the 11th day of April, 2005.
RESOLUTION B
A RESOLUTION AUTHORIZING THE TOWN MANAGER TO AMEND THE SPECIAL USE PERMIT APPLICATION FOR THE SOUTHERN COMMUNITY PARK TO INCREASE THE NUMBER OF PARKING SPACES ON THE SOUTH SIDE OF DOGWOOD ACRES DRIVE (2005-04-11/R-9b)
WHEREAS, on February 21, 2005, the Council opened a public hearing to gather comments related to a Special Use Permit application for the Southern Community Park; and
WHEREAS, during the public hearing the number of parking spaces was identified as a concern; and
WHEREAS, on March 24, 2005, the Council/County Commission Project Planning Committee met and recommended that the Town’s Special Use Permit be amended to show 60 additional parking spaces on the south side of Dogwood Acres Drive; and
WHEREAS, there are insufficient funds to build the proposed northern parking lot along US 15-501; and
WHEREAS, insufficient parking would likely result in park users parking along Dogwood Acres Drive and US 15-501;
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Council authorizes the Town Manager to amend the Town’s Special Use Permit application to propose the construction of 60 additional parking spaces along the south side of Dogwood Acres Drive.
This the 11th day of April, 2005.
RESOLUTION C
A RESOLUTION CONTINUING THE SOUTHERN COMMUNITY PARK SPECIAL USE PERMIT HEARING (2005-04-11/R-9c)
WHEREAS, on February 21, 2005, the Council opened a public hearing to gather comments related to a Special Use Permit application for the Southern Community Park; and
WHEREAS, on April 11, 2005, the Council considered a phasing plan for the project; and
WHEREAS, the Manager has not yet had an opportunity to respond to all of the issues addressed at the February 21, 2005 public hearing;
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Southern Community Park Special Use Permit Public Hearing shall be recessed to May 9, 2005.
This the 11th day of April, 2005.
ATTACHMENT A - CURRENT SPECIAL USE PERMIT PROGRAM
We have submitted a Special Use Permit application for a 70 acre park that, if completely built out, would contain the following infrastructure:
· New street to connect US 15-501 to park and ride lot
· Parking lot (north) with 158 spaces
· Parking lot (south) with 65 spaces
· Sewer and water extensions (including a 12” line to Dogwood Acres Drive; once the future Community Center is built OWASA would expect the 12” line to be continued to Merritt Drive.)
· Restrooms
· Maintenance building
· Sidewalks
· Extension of Fan Branch Greenway Trail to the southern tip of the park property
· Traffic calming on Dogwood Acres Drive
· Extensive landscape buffers along US 15-501
· Dry detention basins
· Constructed wetland basins
· Public art
In addition the program includes the following recreational elements:
· Basketball courts (2)
· In line hockey court (1)
· Picnic Shelters (1 large, 1 small)
· Children’s play area (1)
· Children’s splash park (1)
· Athletic/soccer fields (3)
· Meadow/grass play area
· Youth ballfield
· Dog park
· Disk golf course