The total acreage of easements and land needed to complete the greenway system is significant. In addition, the program projects an eventual trail program that will require construction of over 28 miles of both unpaved and paved trails to be used for recreation and transportation purposes. The needs outlined in this Plan will require a sustained land acquisition and trail construction effort that will spread the costs over many years.
The Town should look at the
need to acquire open space and trails in both the developed portions of Town
and in the few remaining areas anticipated to be developed in the
future. Acquisition is particularly critical in areas where changes in land
use are occurring rapidly which may preempt or make recreation and public use
more difficult. There are few remaining opportunities for acquisition of
large tracts of land. However, at the time of this report some opportunities
remain; especially in the rural buffer and in areas within Orange County but
outside the Town’s jurisdiction.
The Town
Council partially addressed the issue of setting land acquisition priorities by
adopting a plan for the use of the 1989 parks and open space bond. Of the
total $5 million available, $168,000 was spent for the acquisition of greenways
land.
The policy
guidelines for use of the $3 million Open Space bond funds approved in 1996
have not yet been formulated. The Council has directed the Greenways
Commission to develop recommendations by June 1998.
At the time that this report was prepared the Town had about $1.5 million available from an Open Space bond approval in 2003. Recommended considerations for future land acquisition are listed from highest priority to lowest priority:
1. Critical tracts in danger of immediate development.
2. Land needed to construct trails currently in the planning process.
3. Opportunities to take advantage of low prices or willing sellers.
4. Land that is developable but not in immediate danger.
5. Land in no foreseeable danger of development, but needed for the greenway system.
Although the Town has acquired significant amounts of property, recreation area dedications, and easement dedications along identified greenway corridors these acquisitions have been spread out over the entire proposed greenways system. Only a few identified projects have enough land under Town control that they can be considered for potential development in the near future, without major land acquisition efforts.
In addition, only a select number of projects have any identified funding. Projects with funding are identified in Chart ????, page ???.
These potential projects
include:
Projects that have significant amounts of land under Town control and some identified sources of funding include:
Planning underway in 2004
Construction anticipated for 2007
The Town controls much of the land from Airport Road to Estes Drive Extension, although large gaps in property ownership do exist. The Town and Orange County agreed to spend at least $1,100,000 on this project in 2004. Efforts to design a trail corridor from Airport Road to Seawell School Road were started in the fall of 2004. Additional funds from the Town’s 2003 Parks bond could be become available in 2006.
This project would likely be the single most difficult greenway section undertaken by the Town due to the significant physical constraints along this section of Bolin Creek. However, it is a vital link if the Town is to merge its trail system with the future trail systems of Carrboro and Orange County. In addition, this section is a vital link to the Town’s own proposed Rail and North Trails. The combined Rail Trail, North Trail, and Bolin Creek Trail system could eventually provide safe, efficient, bicycle and pedestrian transportation from the Town’s northwest area to neighborhoods in southeast Chapel Hill. Eventually, major destinations would include a number of Town facilities and parks, UNC’s Carolina North campus, and several commercial areas.
Dry Creek (East Chapel Hill High School to Eastowne)
Planning for Project 1 completed, Project 2 underway in 2004, and Project 3 anticipated for 2006
Construction anticipated for 2005 (Projects 1 and 2) and 2009 (Project 3)
Fan Branch (Scroggs School to Merritt Drive)
Planning underway in 2004
Construction anticipated for 2005
Meadowmont Nature Trail (Rashkis School to Lancaster Drive and Meadowmont Road)
Planning complete
Construction underway in 2005
Morgan Creek (Merritt Pasture to Smith Level Road)
Planning underway in 2004
Construction anticipated in 2007
This would be an extension of the existing Fan Branch Trail, which currently ends at Culbreth Road. The main trail would extend about 1 mile to the west along Morgan Creek as a paved bicycle compatible trail. The trail would terminate at Smith Level Road. A natural surface spur trail would extend to the east to Merritt Pasture.
At the time this report was prepared the Town was in the process of planning for the project. In late 2004 the Town started a flood model exercise that should determine bridge locations and allow completion of a concept plan in 2005. The Town has acquired most of the land needed to complete this greenway segment.
Upper Booker Creek (Weaver Dairy Road to Homestead Park with a spur to Rail Trail corridor)
Planning anticipated for 2006
Construction anticipated for 2009)
Dry Creek,
Phase I
(Silver Creek
Trail to Perry Creek Drive)
Dry Creek,
Phase II
(East Chapel
High School to Silver Creek Trail)
The Town
currently owns or expects to own the majority of the Dry Creek corridor from
the new Chapel Hill East High School on Weaver Dairy Road to the Eastowne
office development. Phase II trail construction is anticipated to begin in
Summer 1998.
Lower
Booker Creek, Phase II
(Booker Creek Road to Franklin Street)
Acquisition
of one two-acre property and the expansion in the width of an existing easement
would allow the Town to complete the Booker Creek Trail. The Town Council
authorized the project in September 1997 utilizing $14,000 from the Town’s
General Fund, $56,000 from Metropolitan Planning Organization (MPO) direct
allocation funds and $260,000 from an NCDOT Bicycle Program grant.
Upper
Booker Creek
(Weaver Dairy
Road to Homestead Park)
The Town owns all of the
properties needed to build this proposed trail corridor. The Greenways
Commission anticipates presenting a draft Conceptual Plan to the Town Council
in 1998.
(Airport Road
to Estes Drive Extension)
The Town
controls much of the property from Airport Road to Estes Drive Extension.
These lands include most of what would be required to build a trail from
Village Drive to Pritchard Avenue Extension. Some land acquisition would still
be required, especially from Airport Road to Umstead Park.
Morgan
Creek
(Smith Level
Road to Merritt Pasture)
The Town has acquired
about half the land needed to complete this greenway segment. Payment-in-lieu
from the development of the Southern Village is anticipated in the year 2001
and will fund the construction of a bridge in this corridor.