DRAFT SCHEDULE FOR NEGOTIATING
DEVELOPMENT AGREEMENT
June 15, 2005
Date Task
June 15, 2005 Council consideration of resolution authorizing Manager to begin development agreement negotiations, and to enter into an Exclusive Right to Negotiate with the selected developer; Council consideration of SPPRE contract amendment
June 20, 2005 Council meeting with Ram Development Company to discuss design and building program issues
June 27, 2005 Council consideration of authorizing Exclusive Right to Negotiate between developer and Town
July, 2005 Developer to review and refine proposed building program, including potential participation of RBC Centura
SPPRE to identify “deal points”
Late July, 2005 Initiation of work of Negotiating Team – work to continue through August
Week of August 29, 2005 Meeting of Council Committee to review proposed building program, including financial deal points
September, 2005 Negotiating Team to meet intensively to complete a proposed Development Agreement
Late September, 2005 Meeting of Council Committee to review draft Development Agreement
October 10, 2005 Town Council consideration of Development Agreement