AGENDA #4b

 

MEMORANDUM

 

TO:                  Mayor and Town Council

 

FROM:            W. Calvin Horton, Town Manager

 

SUBJECT:       Bid:  Homestead Park Batting Cage

 

DATE:             April 10, 2000

 

The attached resolution would accept the negotiated bid of R & G Construction Company in the amount of $255,157 and establish a project budget within the 1996 Parks bond fund of $284,000 for this project. The resolution would also authorize the Manager to execute an agreement that would accept a $40,000 contribution from Ryan’s World of Chapel Hill, Inc., the current concessionaire/operator of the Chapel Hill Skate Park, to be used for construction of the Chapel Hill Batting Cage.

 

The attached budget ordinance would increase the 1996 Parks bond fund by $40,000 to reflect Ryan’s World’s contribution.

 

BACKGROUND

 

On February 23, 1998, the Council authorized the Manager to submit a Parks and Recreation Trust Fund (PARTF) grant application that, if it had been awarded, would have partially funded a batting cage facility. The cost estimate for batting cage construction presented to the Council was $196,000, with additional costs including contingency, design, testing, and other costs totaling $256,000. The Town did not receive the grant.

 

On September 16, 1998, the Parks & Recreation Commission petitioned the Council to authorize the start of design work for a batting cage facility at Homestead Park.

 

On September 28, 1998, the Council authorized the staff to begin planning for a batting cage facility at Homestead Park. The staff presented revised cost estimates based on telephone surveys of owners of recently completed batting cage facilities. At that time we estimated construction and design costs to be about $200,000. The Council authorized the staff to use remaining funds from the Lincoln restroom, Northside Gymnasium, and Homestead Park projects for the design and construction of the batting cages. The Council also authorized the use of additional 1996 Parks bonds for this project.

 

On October 27, 1999 the Council authorized the execution of a concession agreement with Ryan’s World of Chapel Hill Inc. for operation of the Chapel Hill Skate Park and the batting cage facility (if built).

On November 22, 1999, the Council rejected the Batting Cage construction bids that were received on October 15, 1999, and authorized the re-bidding of the project.  The low bid was $299,500.

 

The project was re-bid with a bid opening on February 8, 2000.

 

BID PROCESS

 

The Notice To Bidders was published in The Chapel Hill News and the News & Observer on Wednesday, January 5, 2000, and the Challenger Newspaper on Thursday, January 6, 2000.  Bid notices were mailed to nineteen (19) vendors, and two (2) minority business organizations in North Carolina.  Four (4) bids were received on Tuesday, February 8, 2000, 3:00 p.m., and were publicly opened and read as follows:

 

   VENDOR                                                                    BID

 

Patriot Building Co., Inc.                                                           $299,400

Hillsborough, NC

 

KAD Construction, Inc.                                                            $317,000

Raleigh, NC

 

Polovich Construction Co., Inc.                                                $295,400

Raleigh, NC

 

R & G Construction Company                                      $268,980

Charlotte, NC

 

EVALUATION OF BIDS

 

The four (4) bids have been reviewed by Town staff.  We found that the bid proposals met the criteria listed in the bid instructions.  R & G Construction Company’s bid price of $268,980 was the lowest bid.

 

We have since discussed the bid price with R & G Construction and have been able to identify $13,823 in savings. The attached resolution would authorize the construction of the batting cage for the negotiated price of $255,157. The reduction is in line with the Parks & Recreation Commission’s recommendation. Please see attached memorandum from the Parks & Recreation Commission.

 


DISCUSSION

 

The site of the proposed Chapel Hill Batting Cage was originally proposed to be used for tennis courts. However, in the past several years, tennis court use has declined somewhat and stabilized at a level that we believe does not warrant the construction of new courts in Town.

 

In 1998, the Parks and Recreation Commission recommended that a revenue producing facility be built on the site in conjunction with the skate park. The Council authorized the construction of a concession/restroom building that could be used to service both the skate park and a possible batting cage facility. Also in 1998, the Council authorized the staff to pursue the batting cage project.

 

Benefits of Construction of a Batting Cage Facility

We believe that if the batting cage facility is constructed that it would provide the following benefits to the Town:

 

·        The batting cage would be a unique public facility in the Chapel Hill/Carrboro area that would serve both youth and adult users, including many persons in Town athletic leagues.

·        The batting cage, if built, would be operated by the same concessionaire that currently operates the Chapel Hill Skate Park. The concessionaire would be responsible for all expenses including maintenance, salaries, and utilities and bearing the business risk.

·        The concession/restroom building was designed for the addition of a possible future batting cage. Once built, the facility could be managed from the current building with no additional capital costs.

·        The batting cage facility could provide a second revenue generating business adjacent to the skate park. Under the terms of our current agreement with the skate park operator, the Town would receive 10% of all revenues produced from the batting cage facility.

·        Batting cage revenues combined with Skate Park revenues would increase the likelihood of financial success of the concessionaire-as-operator concept.

·        The concessionaire/operator has offered to contribute $40,000 toward the cost of construction of a batting cage in order to bring the Town’s direct costs closer to original estimates.

 

 

Costs of Building a Batting Cage Facility

We believe that the major issues related to construction of the batting cage are:

 

·        The anticipated $244,000 in Town funds recommended for a project budget could be used for some other project, including a proposed aquatics facility.

·        The funds used for building a batting cage facility could be held in reserve in the event that replacement turf is needed on the two ballfields.

·        In the event that the concessionaire elects to terminate the current agreement the Town would be responsible for managing the facility.

·        The 16,500 square feet of land could be used for a number of other projects such as tennis courts, in-line hockey court, or a carousel. Those opportunities would be lost if the batting cage facility is built.

 

 

BUDGET

 

If the Council chooses to authorize construction of the Batting Cage facility we would propose the following project budget, which we believe would allow us to respond to unanticipated field conditions, especially the possibility of dealing with excessive rock. During construction of Homestead Park we removed excessive rock from several areas near the site of the proposed batting cage facility.

 

            Proposed Budget

Construction (negotiated bid price)                                                       255,000

Additional Rock Allowance                                                                   10,000

Materials, Soil and Rock Testing                                                              5,000

Legal                                                                                                       1,000

Contingency (5%)                                                                                  13,000

 

Total Budget                                                                                   $284,000                       

 
RECOMMENDED SOURCES OF FUNDS

 

If the Council chooses to pursue this project, we believe the following sources of funds would be best way to pay for the construction of a batting cage facility.

 

            Recommended Source Of Funds

Contribution from Concessionaire                                                          40,000

Remaining Funds Homestead Park                                                       101,000

Remaining 1996 Parks Bond funds                                                       143,000

 

Total Funds                                                                                     $284,000           

 

Contribution from Concessionaire: Ryan’s World of Chapel Hill, the current concessionaire for the Chapel Hill Skate Park (and any future batting cage facility) has offered to contribute $40,000 toward construction of the batting cage facility. Please see the attached letter from the concessionaire. Ryan’s World proposes to pay for its contribution over a period not to exceed 40 months. Payments would be the greater of $1,000 per month or an 70% of the gross receipts from the batting cage (in addition to the payments required by the existing agreement), until the $40,000 total is achieved. At this time, it appears that Ryan’s World will not be able to provide a bond or other form of guarantee of the $40,000 contribution. Without a bond there would be no guarantee that Ryan’s World would make all or any of their scheduled payments. However, preliminary research of other batting cage facilities indicates that the cash flow from the batting cage might be sufficient to raise the needed cash in 40 months or less. The attached Resolution contains a provision that the acceptance of the bid is contingent upon successful execution of an agreement between the Town and the concessionaire.

 

Remaining Funds Homestead Park:  The Council budgeted a total of $4,607,000 for the completion of Homestead Park from a number of sources including 1996 Parks bond, Capital Improvements Program, 1997 Orange County Parks bonds, payment in lieu of recreation area, and gifts. We now have approximately $175,000 remaining in the Homestead Park project account; all of it from the 1996 Parks bond proceeds.

 

Most of the Homestead Park project is complete, however we do anticipate several remaining expenditures including park signs, electric panels and timers for the athletic fields, court surfacing, and replacement of cracked sidewalks. These projects are anticipated to cost about $74,000. We believe that this would leave about $101,000 in the Homestead Park project account at the conclusion of the remaining work.

 

In addition, it is possible that problems with the turf on the two Homestead Park ballfields may require treatment that could cost in excess of $100,000. The fields have been seeded and sprigged with Bermuda grass. We hope that with proper fertilization and maintenance the turf will be adequate for our purposes. However, the soils at Homestead Park are very poor and may ultimately require the importation of sod. The Council authorized the use of sod for the two soccer fields because of the type of play expected for soccer fields. We should have a better idea whether or not the current ballfield turf will prosper by mid- summer.

 

Remaining 1996 Parks Bond Funds: This proposal would use $143,000 of the currently unallocated $1,364,000 in 1996 Parks Bond funds.

 

Although the Council has not formally allocated these funds the Council has indicated that they would be used for a proposed aquatics facility at Homestead Park. We would have $2,219,000 for the proposed aquatics center if all the Town’s remaining 1996 Parks Bond funds were combined with the $855,000 remaining from the $1,000,000 portion of the 1997 Orange County Parks bond that was committed to Homestead Park. The County has already authorized the use of $145,000 for use in the Homestead Park project. We believe that an aquatic facility would cost a minimum of $3.5-4.5 million. A citizens committee is currently preparing a conceptual plan report for an aquatics facility, which is anticipated to be ready for presentation to the Council in September 2000.

 

SCHEDULE

 

If the Council chooses to proceed with this project we would expect to use the following schedule:

 

Accept Bid                               April

Execute Contracts                    May

Begin Construction                   June

Complete Construction August

Open Facility                            September

SUMMARY

 

The skate park was originally designed to accommodate a batting cage facility. The design would allow both facilities to be operated by a single manager. We continue to believe that the best use of the site would be a revenue producing amenity that could be operated jointly with the skate park. We believe the current concessionaire is capable of managing both facilities in a manner that would bring a positive revenue flow to the Town. We also believe that the batting cage would serve a wide range of participants including both youth and adults. The current skate park concessionaire has offered to contribute $40,000 toward construction of the batting cage over a period not to exceed 40 months. However, it appears that there will be no bond to guarantee that all or any of the payments will be made.

 

If the Council builds the batting cage facility, funds would be spent that could be used for other projects including a proposed aquatics facility, or if necessary, the addition of sod to the Homestead Park ballfields.

 

RECOMMENDATIONS

 

Parks & Recreation Commission’s Recommendation:  At its February 16, 2000 meeting the Parks and Recreation Commission voted unanimously (7-0) to recommend that Council accept the low bid on the batting cage project with the understanding that staff will work with the low bidder to reduce the cost by $12,000 to $15,000. The Commission also understands that a private donor will give $40,000 for the project. This recommendation is contingent on the Town negotiating an agreement with a concessionaire for the Town to receive 10% of revenue and on setting user fees based on comparable regional rates.

 

The Commission reiterated its strong support of the project and stressed the importance of constructing the batting cages as soon as possible.

 

Manager’s Recommendation:  That the Council adopt the attached resolution which would accept the bid of R & G Construction Company for the negotiated amount of $255,000 for the construction of the Homestead Park batting cage, contingent upon the successful execution of an agreement with Ryan’s World of Chapel Hill for the provision of $40,000 to be used for the construction of the batting cage facility.

 

ATTACHMENTS

 

1.      Parks & Recreation Commission Recommendations

2.      Letter from Frank Noel

 


A RESOLUTION TO AWARD THE BID FOR THE HOMESTEAD PARK BATTING CAGE (2000-04-10-/R-3)

 

WHEREAS, the Town of Chapel Hill has solicited formal bids by legal notice in The Chapel Hill News and the News & Observer, January 5, 2000, and the Challenger Newspaper, January 6, 2000, in accordance with N. C. General Statute 143-128 for construction of the batting cage; and

 

WHEREAS, four (4) bids were received on Friday 8, 2000, at 3:00 p.m., and opened:

 

VENDOR                                                                 BID

 

Patriot Building Co., Inc.                                                   $299,400

Hillsborough, N. C.

 

KAD Construction, Inc.                                                    $317,000

Raleigh, N. C.

 

Polovich Construction Co., Inc.                                         $295,400

Raleigh, N. C.

 

R & G Construction Company                                          $268,980

Charlotte, N. C.

 

WHEREAS, the low bidder R & G Construction Company has agreed to a negotiated price of $255,157;

 

NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Town accepts the bid of R & G Construction Company for the negotiated amount of  $255,157 for the construction of the Homestead Park Batting Cage facility contingent upon successful execution of an agreement with Ryan’s World of Chapel Hill that would provide a $40,000 contribution to the Town toward construction of the facility.

 

BE IT FURTHER RESOLVED by the Council that the Manager is authorized to establish a project budget of $284,000 using $244,000 in 1996 Parks bond funds and a $40,000 contribution from Ryan’s World of Chapel Hill, Inc.

 

BE IT FURTHER RESOLVED by the Council that the Manager is authorized to execute an agreement with Ryan’s World of Chapel Hill for the purpose of securing a $40,000 contribution to the Town for construction of a batting cage facility at Homestead Park and establishing rates for use of the batting cage facility that are comparable to other batting cage facilities located in the Triangle.

 

This the 10th day of April, 2000.


AN ORDINANCE TO AMEND THE 1996 PARKS BOND PROJECT ORDINANCE

(2000-04-10/O-0.1) 

 

BE IT ORDAINED by the Council of the Town of Chapel Hill that, pursuant to Section 13.2 of Chapter 159 of the General Statutes of North Carolina, that the capital projects ordinance for various capital projects funded from a variety of sources is hereby amended as follows:

 

SECTION I

 

The capital projects as authorized by the Town Council includes various capital projects funded from grants, the Capital Improvements Program funds, and other miscellaneous sources of revenue for a variety of projects extending beyond one fiscal year.

 

SECTION II

 

The Manager of the Town of Chapel Hill is hereby directed to proceed with implementation of these projects within terms of funds appropriated here.

 

SECTION III

 

Revenues anticipated to be available to the Town to complete the project are as follows:

 

                                                                        Current Budget            Revised

Bond Proceeds                                                         5,000,000                    5,000,000

Interest Earnings                                                                        19,600                         19,600

Other Revenues                                                                       217,200                       257,000

Total                                                                                    5,236,800                    5,236,800

 

Amounts appropriated are for the project as follows:

 

Parks and Recreation Facilities                                                5,236,88                    5,276,800

 

SECTION IV

 

The Manager is directed to report annually on the financial status of the project in an informational section to be included in the Annual Budget, and shall keep the Council informed of any unusual occurrences.

 

SECTION V

 

Copies of this projects ordinance shall be entered into the Minutes of the Council and copies shall be filed within 5 days of adoption with the Manager, Finance Director and Clerk.

 

This the 10th day of April 2000.