AGENDA #5c
MEMORANDUM
TO: Mayor and Town Council
FROM: W. Calvin Horton, Town Manager
SUBJECT: Information Report: Landscape Issues related to the Lower Booker Creek Greenway, Phase II Project
DATE: June 26, 2000
On June 12, 2000, the Council approved the bid of R & G Construction Company in the amount of $373,422 for construction of the Lower Booker Creek Trail. The trail will be a 10-foot wide concrete path that will extend for about 4,300 feet from Booker Creek Road to East Franklin Street.
At that time, the Council directed the Manager to re-examine the costs and benefits associated with landscaping the current Phase I Trail and eliminate any plantings that were purely decorative. The landscape alternative for the Daley Road and Tadley Drive trailheads was expected to cost $10,018 if installed as originally designed.
We will revise the Zoning Compliance Permit for the project to reflect the elimination of these 33 plants. We will then process a change order to give the Town a credit in the amount of $4,178.
We expect the remainder of the plants to be installed in November 2000.