AGENDA #9
TO: Mayor and Town Council
FROM: W. Calvin Horton, Town Manager
SUBJECT: Bids: Construction of Southern Fire Station (#5)
DATE: November 27, 2000
The attached resolutions address the bids received to construct the southern fire station. The budget ordinance would establish a project budget.
Resolution A would accept the lowest responsive bids without change and would authorize the Manager to reduce the scope of the building in order to reduce the overall cost of the project.
Resolution B would accept the lowest responsive bids and award contracts for the construction of the Southern Fire Station (#5).
Resolution C would reject all bids and authorize the Manager to rebid the project.
The attached budget ordinances would increase the current project ordinance established earlier for this project by $223,000 to provide additional funding necessary to co0mplete the project as recommended in discussions below.
The Town Council has allocated $1,300,000 of the 1996 Public Safely Bonds issue of $2 million for the construction and equipping of a southern fire station. Of this total, $300,000 has been encumbered towards the purchase of a fire pumper.
In April 1998 the Council authorized the purchase of 8.72 acres at the southeast corner of Bennett Rd. and 15-501 south for the purpose of siting a fire station and preserving open space. Approximately 1.1 acres of the site has been subdivided for the fire station.
In November 1998 the Council appointed a Citizens Fire Station Design Committee and charged them with the selection of an architect and working with that architect on the design of the project. This committee included two Council members, two neighborhood association representatives, a Citizen’s Energy Task Force representative and Town Staff representing the Manager, Fire, Police, Engineering, Public Works and Planning Departments. In February 1999 Michael Hining Architects (MHA) was selected. The Town Council approved the preliminary design in October, 1999.
Project Description:
The Southern Fire Station (#5) is designed to regularly house a crew of four firefighters, with room for eight during major emergencies. It will also provide a bay area for two large fire apparatus. The 5,165 square feet includes two apparatus bays, four dormitories, two shower/restrooms, one public restroom, a kitchen, dayroom (living and dining), storage/utility rooms, Station Captain’s office, hazardous decontamination room, public reception area, patio area and work areas.
The notice to Bidders was published in the October 4, 2000, edition of the Chapel Hill News and the Chapel Hill Herald and in the October 5, 2000 edition of the Challenger Newspaper, Wilmington, North Carolina. Specifications, plans and contract documents were available for inspection in the office of Michael Hining Architects; and Plan Rooms of the Associated General Contractors in Raleigh, Fayetteville and Greensboro, N.C., at Dodge SCAN, Atlanta, Ga. and Construction Market Data Plan Room in Raleigh, N.C.
On Wednesday, November 1, 2000, at 3:00 p.m., we received sealed bids for the construction, electrical, mechanical and plumbing work for the construction of the Southern Fire Station. In accordance with North Carolina General Statute 143-128, the following bids were received. The figures below are the adjusted bids, calculated by Michael Hining Architects, which reflect equivalent base bid numbers with unit pricing allowances deducted. Unit prices given by contractors were included to address potential, unforeseen site conditions; and were removed to show true base bid numbers for the work specified. Adjusted bids ensure a level playing field when comparing the bid amounts.
|
|
ADD ALTERNATE BIDS |
||||||
Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
||||
McKenna Construction |
$1,048,500 |
$34,500 |
$42,000 |
$1,952 |
||||
Poythress Construction |
$1,015,000 |
$26,500 |
$18,000 |
$2,500 |
||||
Multiple Prime Contracts
|
|
ADD ALTERNATE BIDS |
||
General Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
C. T. Wilson |
$907,643 |
$560 |
$19,435 |
$3,371 |
Engineered Construction Company |
$802,250 |
$1,200 |
$2,750 |
|
Force Construction |
$845,605 |
$890 |
$12,960 |
$2,385 |
Keck Company |
$809,500 |
$17,136 |
$924 |
|
McKenna Construction |
$804,125 |
$42,000 |
$1,952 |
|
Poythress Construction |
$776,875 |
$18,000 |
$2,500 |
|
Resolute Building Company |
$764,925 |
$17,100 |
$2,000 |
|
Shalimar Construction |
$599,250 |
$3,300 |
$4,500 |
|
Van Thomas Contractor |
$968,8750 |
$18,500 |
$2,300 |
|
ADD ALTERNATE BIDS |
|||
Electrical Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Norina Construction |
$79,900 |
$27,500 |
||
Pendergraph Electric |
$80,750 |
$21,990 |
||
Triangle Electrical Services |
$72,500 |
$22,500 |
||
Watson Electric |
$78,550 |
$21,000 |
||
Wood Electric |
$76,200 |
$22,300 |
||
|
||||
|
ADD ALTERNATE BIDS |
|||
Mechanical Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Carolina Air Conditioning |
$37,724 |
|||
Cooper Mechanical |
$34,000 |
|||
|
||||
|
ADD ALTERNATE BIDS |
|||
Plumbing Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Acme Plumbing |
$115,000 |
|||
Brown Brothers Plumbing |
$163,625 |
|||
Eakins Plumbing |
$114,000 |
|||
Progressive Plumbing and Piping |
$98,277 |
|||
Sparrow Plumbing |
$76,633 |
|||
Vickers & Ruth |
$79,069 |
Two companies bid the project as single prime contractors and twenty-two companies bid the project as multi-prime contractors. The sum of the lowest responsive general, plumbing, mechanical and electrical multi-prime bids is lower than each of the two single prime bids. Therefore, four prime contactors will build this project, each working directly for the Town, with the work coordinated by the general contractor.
The bid of Sparrow Plumbing was determined to be unresponsive due to omissions and oversights. The bid of Shalimar Construction was withdrawn because of an arithmetic error.
The remaining bids of the general contractors were analyzed and, so noted above, then adjusted to remove unit price allowances for potential site work. Unit prices for such work had been requested with the bids to set prices for site work which may arise during construction. The lowest responsive bids from general contractors bidding as multi-primes are: Resolute Building Company ($764,925); Triangle Electrical Services ($72,500); Vickers & Ruth Plumbing ($79,069); and Cooper Mechanical ($34,000) for a total of $950,454.
Initial estimates, developed in 1996, assigned a project budget of $1,000,000 in preparation for the 1996 Public Safety Bond. This amount was funded through the 1996 Public Safety Bond referendum and was ear marked for design, land acquisition and construction of the station. During the design and development phase of the project, cuts were made to the building program and design in an attempt to stay within the $1,000,000 budget. With the receipt of the construction bids, the deletion of all alternate and additional cuts will be required to keep the project within the budget. . For purposes of this memorandum, construction figures from the low multi-prime bidders are used for actual budget figures. The cost savings for deleted items have been negotiated with Resolute, pending Council approval.
Below are the projected costs of the project.
Option A |
Option B |
|
Acquisition of Land |
$24,157 |
$24,157 |
Architectural Design |
$82,000 |
$82,000 |
Legal Fees |
-$0- |
-$0- |
Construction Management |
-$0- |
-$0- |
Furniture and Equipment |
$60,000 |
$60,000 |
Tap On Fees for OWASA |
$6,000 |
$6,000 |
Testing |
$4,000 |
$4,000 |
Construction Costs |
$936,044 |
$1,005,494 |
Utility Work |
$55,000 |
$55,000 |
General Contractor |
$695,475 |
$764,925 |
Electrical Contractor |
$72,500 |
$72,500 |
Plumbing Contractor |
$79,069 |
$79,069 |
Mechanical Contractor |
$34,000 |
$34,000 |
1% of Construction for Art |
$10,054 |
$10,054 |
Contingency Fund (10%) |
$100,549 |
$100,549 |
TOTAL: |
$1,222,804 |
$1,292,254 |
Funding for the Southern Fire Station is $1,000,000 from the 1996 bonds. The cost for acquiring the land was less than projected, but costs to provide water and sewer to the site were considerably more than expected. The cost of extending water and sewer lines from Bennett Road to the existing mains in Southern Village is being shared equally by the developer of One Hundred Oaks, as a part of the agreement to buy the fire station site. Nevertheless, DOT’s improvements to the US 15-501/Bennett Road intersection have increased the cost of utilities and changes in DOT’s plans increased the cost of design work.
From the start of the design process, it was clear that the budget was very limited. In fact, when the conceptual design was presented to the Council, the following items were removed: a community meeting room, office space to function as a police sub-station, a pull through apparatus bay with circular drive and a fitness/workout room for fire and police employees stationed in the southern district. Although each of these features was reasonably warranted, the final bid documents were pared to include only those elements absolutely necessary to the function of the fire station, as well as what is necessary to meet the ordinance requiring Town buildings to be 30% more energy efficient that the State Building Code requires, regulations of the Occupational Safety and Health Administration (OSHA), and the standards of the American with Disabilities Act.
Nevertheless, after reviewing the bids submitted, we worked with our architects, engineers and Resolute Building Company to identify additional savings that might be possible. We considered and discarded suggestions, which would contradict clear Council policies, such as deleting the sprinkler system, deleting the bio-retention pond and water garden, and replacing the aerated concrete blocks with standard framing. We do, however, recommend a list of other changes and deletions, which would save a total of $69,450. The most obvious change, substituting an angled, single-pitch shingled roof for the rounded, standing seam metal roof over the equipment bay carries with it the bulk of the cost savings proposed: $45,000.
We itemize below potential money-saving changes, the negotiated cost savings and explain the impacts of each. Attachments 1, 2, and 3 describe them in greater detail. Also, the sketches in Attachment 4 through 6 show the recommended changes.
OPTION A
(Change project, save $69,450 and use $222,804 additional funds)
We believe that the following reductions can be implemented with little or no negative impacts to the energy-efficient design proposed by the architect:
Cost reduction: $10,000.
Cost reduction: $6,200
Cost reduction: $45,000 .
Cost reduction: $900.\
Cost reduction: $950.
Cost reduction: $1,300.
Cost reduction: $1,100.
Cost reduction: $4,000.
The total amount of savings to be achieved by the above reductions is $69,450. The project budget would need to be increased by $222,804. If this approach were taken, we would recommend that additional funds be transferred from the following places:
Anticipated interest earnings
on public safety bond proceeds
$120,.000
Final unallocated fund balance from Capital Reserve Fund 75,000
General Fund Balance 28,000
Total $223,000
We anticipate that about $120,000 in interest would be earned on the public safety bonds between the time they were sold in March, 2000 until the fire station project is completed, and recommend allocation of all of this interest to the project. In addition, we recommend allocating the final unallocated fund balance in the Capital Reserve Fund for the fire station project, with the remainder of $28,000 needed for the total project budget from fund balance in the General Fund.
Advantages:
Disadvantages:
The architect and Fire Department staff identified other possible reductions that might be considered. They include:
Cost Reduction: $2,000
Cost reduction over roof originally specified: $45,000
Cost increase over shingled roof with steel bar joists: $13,500
Cost reduction: $1,100
(Accept bids as received, use $292,254 in additional funds)
The project budget would be increased by up to $292,254. If this approach were taken, we would recommend that additional funds be transferred from the following places:
Anticipated interest earnings
on public safety bond proceeds
$120,.000
Final unallocated fund balance from Capital Reserve Fund 75,000
General Fund Balance 97,000
Total $292,000
Under this option, we recommend the same revenue sources as noted for Option A, except that $97,000 would be required from fund balance in the General Fund to build the project as this level.
Advantages:
Disadvantages:
(Rebid the project)
The Town could reject all bids because they exceed the Town’s budget for the Southern Fire Station construction.
After analyzing the current bids, we believe that rebidding the project without substantial redesign would most likely result in bids that are the same or higher than those already received. We do not think that the basic conditions which resulted in the high bids would change over the next 6 to 9 months. We believe that the number of bids received within a relatively small range suggest that they were reasonable for the type of structure specified and the requirements of the higher energy efficiency standards followed. Additionally, rebidding might result in higher than normal bids because of the increased construction activity related to the recently approved Higher Education Capital Bond.
Rebidding after a redesign could result in lower bids. However, we do not now believe it is realistic to expect that we could design a structure to meet the functional needs of a fire station and do so in a way which uses 30% less energy than the building code would allow, while keeping within the original budget.
Advantages:
Disadvantages:
The bids received for construction of the Southern Fire Station (#5) project, the cost of various associated fees, and the establishment of a reasonable contingency allowance have resulted in a projected project budget deficit of $292,254 if the project is built as designed.
We believe that the Council has three main options. One approach would be to use a combination of reductions in the scope of the project and an increase in the project budget. This approach would limit the needed budget increase to $222,804, while the building would change in appearance from the inside and from the outside.
A second option would be for the Council to accept the current low bids and utilize other funding sources to increase the project budget. This approach would result in construction of the Southern Fire Station as designed, but require that $292,254 be added to the budget.
The third option available to the Council would be to rebid the project. However, we can find no reason to believe that this approach would result in lower bids.
Manager’s Recommendation: That the Council adopt Resolution A accepting the negotiated bids of Resolute Builders, General Contract ($695,475); Triangle Electrical Services, Electric Contract ($72,500); Vickers & Ruth Plumbing, Plumbing Contract ($79,069); and Cooper Mechanical, Mechanical Contract ($34,000) for a total amount of $881,044, for the construction of the Southern Fire Station. In addition, the Manager would be authorized to reduce the scope of the project by making the changes described above in Option A, for a total reduction of $69,450.
With this option, we recommend that the Council adopt the attached budget ordinances increasing the Southern Fire Station project budget by $223,000 from sources as noted above.
Alternate Resolution B would authorize the Manager to accept the bids of Resolute Builders, General Contract ($764,925); Triangle Electrical Services, Electric Contract ($72,500); Vickers & Ruth Plumbing, Plumbing Contract ($79,069); and Cooper Mechanical, Mechanical Contract ($34,000) for a total amount of $950,454, for the construction of the Southern Fire Station.
If the Council adopts Resolution B, the recommended budget ordinances would need to be adjusted to reflect the greater use of $97,000 from fund balance that would be required under this option.
Resolution C would reject all bids and authorize the Manager to rebid the project.
ATTACHMENTS
1. Letter of November 16, 2000 from Michael Hining Arcitects (p. 18).
2. Letter of November 14, 2000 from Michael Dykes (p. 20).
3. Original Design Elevation (p. 22).
4. Alternate Design #1 Elevation (p. 23).
5. Alternate Design #2 Elevation (p. 24).
6. Site Plan Changes (p. 25).
A RESOLUTION ACCEPTING BIDS, AWARDING THE CONTRACTS FOR THE CONSTRUCTION OF SOUTHERN FIRE STATION (#5), AND AUTHORIZING A REDUCTION IN THE SCOPE OF THE PROJECT (2000-11-27/R-11a)
WHEREAS, the Town of Chapel Hill has solicited formal bids by advertisement in The Chapel Hill News on October 4, 2000, The Chapel Hill Herald on October 4 2000, and the Challenger Newspaper on October 5, 2000 and in accordance with G.S. 143-128 for the construction work; and
WHEREAS, the following bids were received and opened on November 1, 2000:
Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
McKenna Construction |
$1,048,500 |
$34,500 |
$42,000 |
$1,952 |
Poythress Construction |
$1,015,000 |
$26,500 |
$18,000 |
$2,500 |
MULTIPLE PRIME CONTRACTS
General Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
C. T. Wilson |
$907,643 |
$560 |
$19,435 |
$3,371 |
Engineered Construction Company |
$802,250 |
$1,200 |
$2,750 |
|
Force Construction |
$845,605 |
$890 |
$12,960 |
$2,385 |
Keck Company |
$809,500 |
$17,136 |
$924 |
|
McKenna Construction |
$804,125 |
$42,000 |
$1,952 |
|
Poythress Construction |
$776,875 |
$18,000 |
$2,500 |
|
Resolute Building Company |
$764,925 |
$17,100 |
$2,000 |
|
Shalimar Construction |
$599,250 |
$3,300 |
$4,500 |
|
Van Thomas Contractor |
$968,8750 |
$18,500 |
$2,300 |
|
|
||||
Electrical Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Norina Construction |
$79,900 |
$27,500 |
||
Pendergraph Electric |
$80,750 |
$21,990 |
||
Triangle Electrical Services |
$72,500 |
$22,500 |
||
Watson Electric |
$78,550 |
$21,000 |
||
Wood Electric |
$76,200 |
$22,300 |
||
|
||||
Mechanical Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Carolina Air Conditioning |
$37,724 |
|||
Cooper Mechanical |
$34,000 |
|||
|
||||
Plumbing Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Acme Plumbing |
$115,000 |
|||
Brown Brothers Plumbing |
$163,625 |
|||
Eakins Plumbing |
$114,000 |
|||
Progressive Plumbing and Piping |
$98,277 |
|||
Sparrow Plumbing |
$76,633 |
|||
Vickers & Ruth |
$79,069 |
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Town accepts the bids and awards contracts to Resolute Builders, General Contract ($695,475); and Triangle Electrical Services, Electric Contract ($72,500); Vickers & Ruth Plumbing, Plumbing Contract ($79,069); and Cooper Mechanical, Mechanical Contract ($34,000) for a total amount of $881,044 for the construction of Southern Fire Station (#5).
BE IT FURTHER RESOLVED that the Council hereby authorizes the Manager to further evaluate all potential cost savings, to reduce the scope of the project where appropriate, and to substitute materials in order to reduce the overall costs for construction of the Southern Fire Station (#5), such changes to substantially follow the list below:
This the 27th day of November, 2000.
RESOLUTION B
A RESOLUTION ACCEPTING BIDS AND AWARDING THE CONTRACTS FOR THE CONSTRUCTION OF SOUTHERN FIRE STATION (#5) (2000-11-27/R-11b)
WHEREAS, the Town of Chapel Hill has solicited formal bids by advertisement in The Chapel Hill News on October 4, 2000, The Chapel Hill Herald on October 4 2000, and the Challenger Newspaper on October 5, 2000 and in accordance with G.S. 143-128 for the construction work; and
WHEREAS, the following bids were received and opened on November 1, 2000:
Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
McKenna Construction |
$1,048,500 |
$34,500 |
$42,000 |
$1,952 |
Poythress Construction |
$1,015,000 |
$26,500 |
$18,000 |
$2,500 |
MULTIPLE PRIME CONTRACTS
General Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
C. T. Wilson |
$907,643 |
$560 |
$19,435 |
$3,371 |
Engineered Construction Company |
$802,250 |
$1,200 |
$2,750 |
|
Force Construction |
$845,605 |
$890 |
$12,960 |
$2,385 |
Keck Company |
$809,500 |
$17,136 |
$924 |
|
McKenna Construction |
$804,125 |
$42,000 |
$1,952 |
|
Poythress Construction |
$776,875 |
$18,000 |
$2,500 |
|
Resolute Building Company |
$764,925 |
$17,100 |
$2,000 |
|
Shalimar Construction |
$599,250 |
$3,300 |
$4,500 |
|
Van Thomas Contractor |
$968,8750 |
$18,500 |
$2,300 |
|
|
||||
Electrical Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Norina Construction |
$79,900 |
$27,500 |
||
Pendergraph Electric |
$80,750 |
$21,990 |
||
Triangle Electrical Services |
$72,500 |
$22,500 |
||
Watson Electric |
$78,550 |
$21,000 |
||
Wood Electric |
$76,200 |
$22,300 |
||
|
||||
Mechanical Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Carolina Air Conditioning |
$37,724 |
|||
Cooper Mechanical |
$34,000 |
|||
|
||||
Plumbing Contractor |
Base Bid |
Generator |
Wallbeds |
Foodlockers |
Acme Plumbing |
$115,000 |
|||
Brown Brothers Plumbing |
$163,625 |
|||
Eakins Plumbing |
$114,000 |
|||
Progressive Plumbing and Piping |
$98,277 |
|||
Sparrow Plumbing |
$76,633 |
|||
Vickers & Ruth |
$79,069 |
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Town accepts the bids and awards contracts to Resolute Builders, General Contract ($764,925); and Triangle Electrical Services, Electric Contract ($72,500); Vickers & Ruth Plumbing, Plumbing Contract ($79,069); and Cooper Mechanical, Mechanical Contract ($34,000) for a total amount of $950,454 for the construction of Southern Fire Station (#5).
This the 27th day of November, 2000.
A RESOLUTION REJECTING ALL BIDS AND AUTHORIZING THE REBIDDING OF THE SOUTHERN FIRE STATION (#5) (2000-11-27/R-11c)
WHEREAS, the Town of Chapel Hill has solicited formal bids by advertisement in The Chapel Hill News on October 4, 2000, The Chapel Hill Herald on October 4 2000, and the Challenger Newspaper on October 5, 2000 and in accordance with G.S. 143-128 for the construction work; and
WHEREAS, bids were received and opened on November 1, 2000; and
WHEREAS, the low responsible bids for the project exceeded the available project budget.
NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Town rejects all bids for the construction of the Southern Fire Station (#5) and authorizes the Manager to rebid the project.
This the 27th day of November, 2000.
AN ORDINANCE TO AMEND “THE ORDINANCE CONCERNING APPROPRIATIONS AND THE RAISING OF REVENUE FOR THE FISCAL YEAR BEGINNING JULY 1, 2000 (2000-11-27O-7a)
BE IT ORDAINED by the Council of the Town of Chapel Hill that the Budget Ordinance entitled “An Ordinance Concerning Appropriations and the Raising of Revenue for the Fiscal Year Beginning July 1, 2000” as duly adopted on June 26, 2000 be and the same is hereby amended as follows:
ARTICLE I
Current Revised
APPROPRIATIONS Budget Increase Decrease Budget
CAPITAL RESERVE
FUND
Transfer to Fire Station
Capital Project Fund 370,000 75,000 445,000
GENERAL FUND
Transfer to Fire Station
Capital Project 0 28,000 28,000
ARTICLE II
Current Revised
REVENUES Budget Increase Decrease Budget
CAPITAL RESERVE
FUND
Fund Balance 370,000 75,000 445,000
GENERAL FUND
Fund Balance 2,299,990 28,000 2,327,990
This the 27th day of November, 2000.
AN ORDINANCE AMENDING THE CAPITAL PROJECT ORDINANCE FOR POLICE AND FIRE FACILITIES AND EQUIPMENT FROM 1996 BONDS (2000-11-27/O-7b)
BE IT ORDAINED by the Council of the Town of Chapel Hill that, pursuant to Section 13.2 of Chapter 159 of the General Statutes of North Carolina, that the following capital project established for construction of a Fire Station and purchase of firefighting equipment and for renovations of the Police Headquarters funded from bonds approved by the voters in November, 1996 is hereby amended as follows:
The capital projects as authorized by bond referenda approved in November, 1996 includes the capital costs of constructing a fire station and purchase of a fire pumper and for renovations and capital improvements to the Police Headquarters.
The Manager of the Town of Chapel Hill is hereby directed to proceed with implementation of these projects within terms of funds appropriated here.
Revenues anticipated to be available to the Town to complete the project are as follows:
Current Revised
Budget Budget
Transfer from Capital Reserve Fund 0 75,000
Transfer from General Fund 0 28,000
Total 2,000,000 2,223,000
Amounts appropriated are for the project as follows:
Fire Facilities and Equipment 1,300,000 1,523,000
Renovations and Improvements to Police Headquarters 700,000 700,000
Total $2,000,000 2,223,000
The Manager is directed to report annually on the financial status of the project in an informational section to be included in the Annual Budget, and shall keep the Council informed of any unusual occurrences.
Copies of this ordinance shall be entered into the Minutes of the Council and copies shall be filed within 5 days of adoption with the Manager, Finance Director and Clerk.
This the 27th day of November, 2000.