AGENDA #10

 

MEMORANDUM

 

TO:                                  Mayor and Town Council

 

FROM:            W. Calvin Horton, Town Manager

 

SUBJECT:                         Downtown Street and Pedestrian Lighting Options

 

DATE:                         December 11, 2000

 

Adoption of the attached resolution would authorize the Town Manager to begin installing custom street and pedestrian lighting for the section of the 100 block of East Franklin Street where the utility duct bank is in place.

 

SUMMARY

 

This report concludes:

 

·        That, considering long-range maintenance costs, it would be more cost effective to pay Duke Power Company for decorative poles and fixtures rather than for the Town to purchase and maintain them.

 

·        That the available funding is sufficient to pay Duke Power Company the estimated $125,778 cost for lighting improvements for a portion of the 100 block of East Franklin Street.

 

·        That a portion of the additional $500,000 in bond funding available in early 2002 could be used to complete all sections of Streetscape construction and lighting improvements in the 100 blocks of East Franklin and North Columbia Streets over the next three years.

 

BACKGROUND

 

In November 1999, Public Works staff presented a report on downtown street and pedestrian lighting options (Attachment 1).  Four scenarios were described in the report together with the advantages, disadvantages, and “ballpark” estimates of the marginal cost increase for each option over what the Town currently pays for downtown lighting.  A summary table from that report can be found on page 18, and illustrations of the alternative poles and fixtures can be found on pages 20 - 22.  The four alternatives for downtown lighting and their estimated installed costs for the entire Streetscape study including maintenance costs over 30 years for options 2 and 3 are listed below:

 

1.      Duke Power Company standard poles and fixtures:                                            No additional cost

  1. Duke Power stock upgraded poles and fixtures:             $1,147,000 including maintenance
  2. Custom poles and fixtures owned by Duke Power:             $1,517,000 including maintenance
  3. Custom poles and fixtures owned by the Town:      $910,000 excluding maintenance

Upon consideration of the staff report, the Council requested that additional information be developed for options 3 and 4, which utilize the custom decorative green fluted poles and pedestrian light fixtures currently in place at Top of The Hill and at the Streetscape demonstration project on West Franklin Street.  Option #1 did not provide the desired lighting improvements.  In option #2, the stock fixtures were less durable and less attractive and provided poorer lighting uniformity than the fixtures proposed in options #3 and #4.

 

The Council also specifically authorized the Town Manager to seek cost estimates from private electrical contractors for installation and maintenance of new custom street and pedestrian lights for a portion of the 100 block of East Franklin Street.  This section of East Franklin Street has had the underground conduit installation necessary to service new fixtures already installed. 

 

The purpose of developing these detailed cost estimates from private contractors was to determine if long-range savings might be realized by using private contractors to install and maintain the preferred decorative fixtures, rather than paying Duke Power Company a one-time fee for installation and maintenance of these same fixtures.  Utilizing a section of the Streetscape project, where necessary infrastructure construction was already in place, was necessary to develop detailed comparative cost estimates. 

 

DISCUSSION

 

Staff met with several contractors and obtained estimates for pole and fixture installation from two of them.  Updated prices were also solicited from Duke Power.  All of the following estimates are for the purchase and installation of six 30-foot fluted metal street light poles with pedestrian lights and street lights, six 15-foot fluted metal poles with pedestrian lights, and two fluted poles with traffic signal mast arms and pedestrian lights.  A map showing the locations of these proposed fixtures is on page 19.

 

Lighting Maintenance Costs:

 

The Duke Power Company purchase option also includes ongoing maintenance for a period of thirty years after installation of the proposed fixtures.

 

If the poles and fixtures are installed by a private contractor, maintenance would need to be provided by Town staff and/or a private contractor.  While a portion of these annual maintenance costs could be predicted for replacing lamps and ballasts, the exact costs for upkeep of poles, fixtures, arms, and receptacles, as well as the cost of emergency repairs would remain uncertain.  One private contractor provided the Town with the following range of likely annual contracted costs to maintain the 14 fixtures proposed to be installed on East Franklin Street:

 

Routine lamp and ballast replacement:                                                                   $1,250/year

Emergency costs due to storms and/or needed electric service repairs:               $1,000/year

Upkeep costs for painting and fixture replacement due to accidents etc.:            $1,000 - $3,000/year

 

Total range for contracted annual maintenance costs:                            $3,250 - $5,250/year

 

Using these annual maintenance cost estimates, the long-range costs for maintenance by a private contractor over the same thirty-year period covered in the Duke Power Company purchase option would be from $97,500 to $157,500 in current dollars.  Although costs might be somewhat lower if Town labor resources were utilized for routine lamp replacements and painting, we anticipate that long-range costs would likely be in the range provided.  Considering this, a thirty-year maintenance cost of $97,500 is used in the following comparison.

 

Detailed Cost Comparison of Private Contractor and Duke Power Company:

 

Installation by Private Contractor:

 

Town purchase of poles and fixtures:                                                                           $39,390

Installation by “Contractor A”:                                                                                      $45,600

Total “Contractor A” installed cost (no maintenance):                                          $84,990

 

Town purchase of poles and fixtures:                                                                           $39,390

Installation by “Contractor B”:                                                                                      $41,500

Total “Contractor B” installed cost (no maintenance):                                          $80,890

 

Thirty-year maintenance cost estimate:                                                                  $97,500

 

Total cost by Private Contractor:                                                           $178,390 - $182,490

 

Installation and Maintenance by Duke Power Company:

 

Total cost by Duke Power Company:                                                                   $125,778

 

These figures suggest that estimated long-range maintenance costs associated with Town purchase of the poles and fixtures may exceed the initial cost of the fixtures.  As a result, we believe that acquiring the poles and fixtures from Duke Power Company is more cost effective.

 

Improvements Available with Current Funding:

 

In 1996 $1,000,000 in Streets and Sidewalks bonds were approved for Streetscape construction. To date, $500,000 has been allocated from bond sales with the additional $500,000 anticipated in early 2002. Of the $500,000 currently allocated, approximately $165,000 has been expended for two sections of Streetscape improvements in the 100 block of East Franklin Street.  In May of 2000, the Council authorized encumbering an additional $60,000 in available funds for construction of improvements associated with the Orange County Skills Development Center in the 500 Block of West Franklin Street.  The estimated remaining balance from the current appropriation is $275,000.

 

A related report, “Downtown Streetscape Construction Options”, included in tonight’s Council agenda, requests authorization to utilize an additional $85,000 for construction of another section of Streetscape improvements by the Town’s Public Works Department in the summer of 2001.  If these funds are encumbered, a total of approximately $190,000 will remain available for lighting or other Streetscape related improvements.

 

The $190,000 currently available for Streetscape improvements is sufficient to cover the cost of providing lighting improvements for a section of East Franklin Street as detailed in the above options.  Considering the long-range maintenance costs, we recommend that if these lighting improvements are undertaken, that they be installed and maintained by Duke Power Company. 

 

Improvements Available with Anticipated Funding:

 

Once the anticipated $500,000 in additional bond funding is available, we believe that it will be possible to construct several more sections of Streetscape improvements and complete all lighting improvements on both sides of the 100 block of East Franklin Street.  Using these funds, we believe that it would also be possible to provide lighting improvements in additional areas, such as the 100 block of North Columbia Street and the section of the 100 block of West Franklin Street where other Streetscape improvements are currently in place.  Detailed estimates for these possible future projects will be provided to the Council as funding becomes available.

 

Consistent with the original Streetscape cost estimates, it will not be possible to complete Streetscape construction and lighting improvements to all sections of Franklin Street and other streets in the Streetscape project area at the anticipated level of funding.

 

Additional Lighting Issues:

 

Recent information received from Duke Power Company indicates that they have revised their policies and will no longer permit unmetered electrical receptacles on Duke Power Company poles to accommodate holiday decorations.  We anticipate that the Town may need to coordinate installation of separate electric service to the new poles if illuminated holiday decorations are to be retained.  We will also negotiate with Duke Power Company to determine if an exception may be possible for the relatively few fixtures proposed to be installed at this time.

 

The cost estimates provided by Duke Power Company in this report are subject to change.  If the Council approves, we will proceed to request the installation of the lights from Duke Power Company.  It is possible that the final cost for the lighting improvements proposed above could exceed the current estimates and, if providing metered service to accommodate holiday decorations is necessary, the total project cost could be around $140,000.

 

The proposed project includes installing two mast arm signal system poles at the mid-block crosswalk in the 100 block of East Franklin Street.  This will involve installing a signal system wire under the pavement to connect the two poles.  Cutting the pavement to do this installation work will require an encroachment agreement from the North Carolina Department of Transportation.  It is possible that an overhead wire would have to be installed temporarily until such time as the encroachment agreement is granted and the underground wire is installed.

 

 

 

RECOMMENDATION

 

We recommend that the Council approve the attached resolution authorizing the Town Manager to begin installing custom street and pedestrian lighting for the section of the 100 block of East Franklin Street where the utility duct bank is in place.

 

ATTACHMENTS

 

1.      Memorandum to Council dated November 8, 1999, “Downtown Streetscape Lighting Options;” (p. 7).

 


A RESOLUTION AUTHORIZING THE TOWN MANAGER TO initiate the formal process as specified by Duke Power Company to BEgin installing custom street and pedestrian lighting for a section of the 100 block of east franklin street where the utility duct bank is in place (2000-12-11/r-15)

 

WHEREAS, the Town Council adopted the Downtown Streetscape Master Plan as part of the Town’s Comprehensive Plan; and

 

WHEREAS, lighting improvements are a fundamental component of the Downtown Streetscape Master Plan; and

 

WHEREAS, $190,000 is currently available from the 1996 Streets and Sidewalks bond revenues to implement downtown lighting improvements; and

 

WHEREAS, long-term maintenance considerations make installation by Duke Power Company the more cost-effective option for a system of custom street and pedestrian lighting;

 

NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Council authorizes the Town Manager to initiate the formal process as specified by Duke Power Company to begin installing custom street and pedestrian lighting for the section of the 100 block of East Franklin Street where the utility duct bank is in place.

 

This the 11th day of December, 2000.