AGENDA 4h
MEMORANDUM
TO: Mayor and Town Council
FROM: Council Member Flicka Bateman
Council Member Bill
Strom
SUBJECT: Follow-up from
DATE:
As a follow-up to the
Resolution A would authorize the Manager to modify the
adopted schedule for extraordinary maintenance of the
Resolution B would authorize the Manager to include the resurfacing of the outdoor
basketball court at the
Extraordinary Maintenance Schedule for the
On
We
believe that the children from the Town’s day camps at
Resolution A would
authorize the Manager to implement a schedule for extraordinary maintenance of
the
Outdoor
Another
issue discussed at the
We
recommend that the Council make these improvements and that the current asphalt
surface be overlaid with a commercial grade sport surface such as are found on
Town tennis courts and the basketball court at the Community Center. These
courts have a surface that is softer than asphalt and easier on players’ legs
and knees. The primary problem with these surfaces is that they have a tendency
to crack and require repairs every 3-6 years.
The staff estimates that the cost of upgrading the outdoor basketball
court surface at the Northside Gymnasium to be about $3,500 which would include
the sports surface and the addition of basketball court boundary lines.
We
recommend that this work be added to the Town-wide court resurfacing project
that is expected to be bid this spring. That project would include major
renovation of the
Resolution
B would authorize the Manager to include the project as part of the tennis and
basketball courts resurfacing project for bid purposes.
RESOLUTION A
A RESOLUTION AUTHORIZING THE MANAGER TO IMPLEMENT A SCHEDULE FOR EXTRAORDINARY
MAINTENANCE OF THE HARGRAVES CENTER AND A.D. CLARK POOL THAT WOULD RESULT IN AN
APRIL 2002 CONSTRUCTION START FOR BOTH FACILITIES (2002-01-14/R8a)
WHEREAS, the Council has adopted a Capital Improvements Program budget
that includes renovations for the
WHEREAS, the consensus of residents attending the December 13, 2001,
community meeting regarding the extraordinary maintenance project was that the Town should
proceed with the renovation of both the community center and the pool as soon
as possible, even if that were to mean not having the pool open at all in 2002;
and
WHEREAS, an April start of construction would allow for an earlier completion
of work on the project;
NOW,
THEREFORE, BE IT RESOLVED by the Council of the Town of
BE
IT FURTHER RESOLVED that the Council authorizes the Manager to submit an
application to the Local Government Commission for installment financing of
this project and to schedule a Public Hearing.
This the 14th day of January, 2002.
RESOLUTION B
A RESOLUTION AUTHORIZING THE MANAGER TO INCLUDE THE RESURFACING OF THE
OUTDOOR
WHEREAS, the consensus of residents attending the December 13, 2001community
meeting regarding the Hargraves Center extraordinary maintenance project was
that the
Town should resurface the outdoor basketball court adjacent to the Northside Gymnasium;
and
WHEREAS, this work could be added to the Town-wide tennis and
basketball court resurfacing project that is expected to be bid this spring;
NOW,
THEREFORE, BE IT RESOLVED by the Council of the Town of
This the 14th day of January, 2002.