ATTACHMENT 2
A RESOLUTION PROVIDING
COMMENTS TO THE DURHAM-CHAPEL HILL-CARRBORO TRANSPORTATION ADVISORY COMMITTEE
ON THE U.S. 15-501 MAJOR INVESTMENT STUDY, PHASE II REPORT. (2001-10-22/R-9)
WHEREAS, the Durham-Chapel
Hill-Carrboro Transportation Advisory Committee has initiated a Major
Investment Study for the U.S. 15-501 corridor between Durham and Chapel Hill;
and
WHEREAS, the Phase II Report,
reviewing possible fixed guideway alignments and technologies in the U.S.
15-501 corridor, has been completed; and
WHEREAS, the Town of Chapel Hill
has participated in development of the Phase II Report; and
WHEREAS, the Town Council has
reviewed the Phase II Report and recommendations of the U.S. 15-501 Major
Investment Study Policy Oversight Committee.
NOW, THEREFORE, BE IT RESOLVED
that the Council of the Town of Chapel Hill that the following comments and
recommendations be provided to the Durham-Chapel Hill-Carrboro Transportation
Advisory Committee:
- The fixed guideway alignment
identified in the Phase II Report should be included in the Durham-Chapel
Hill-Carrboro 2025 Transportation Plan and should be protected by local
jurisdictions for future use.
- Regarding the alignment
proximate to any school site in the area we request that the Town Council
have an opportunity to communicate with and obtain the advice of the
Chapel Hill Carrboro School Board before any decisions are made.
- Light Rail, busway and bus in
mixed traffic technologies evaluated in the Phase II Report should be
included in future analysis.
- The federal Environmental
Impact Statement process for implementing the fixed guideway corridor
should be initiated as soon as possible.
BE IT FURTHER RESOLVED, that the
following items should be addressed to complete the Phase II Report:
- Revise the No Build Alternative
to better reflect the 2025 transit network. The revised No Build
alternative should be analyzed and the estimate of new riders included in
the Evaluation Matrix.
- Include an assessment of the
impact of all alternatives on daily and peak hour congestion along U.S.
15-501 and adjacent roadways.
- Include capital and operating
data for the No Build alternative in the Evaluation Matrix
- Complete the separate
evaluation of the possible use of Manning Drive for the bus in mixed
traffic alternative.
BE IT FURTHER RESOLVED, that the
following items should be addressed in any further evaluation of the fixed
guideway alternatives in the U.S. 15-501 corridor:
- Allow adequate time to review
and revise modeling of fixed guideway alternatives.
- Refine the feeder bus networks
to maximize the fixed guideway corridor ridership.
- Revise the zonal structure and
projected 2025 median annual incomes for the zones around the Meadowmont
Station.
- Include electric Light Rail as
an alternative rail technology.
- Review the experience of other
regions with similar land use patterns to determine the most appropriate
type of fixed guideway system.
- Include stated preference
factors in the analysis of various technologies.
This the 22nd day of
October, 2001.