TOWN OF CHAPEL HILL DRAINAGE ASSISTANCE PROGRAM
|
||
LOCATION AND DESCRIPTION |
ESTIMATED COST |
SCORE (LOW, MODERATE, HIGH) |
Replace culvert and make channel improvements at: Burning Tree Drive |
$100,000 |
HIGH |
Install pipe at: 105 St. Andrews Place |
2,500 |
MODERATE |
Replace pipe at: 214 Sharon Road |
7,600 |
MODERATE |
Install curb inlets on: Rosemary Street |
9,350 |
MODERATE |
Slip-line pipe at: 1605 Ferrell Road |
9,500 |
MODERATE |
Replace pipe at: Piney Mountain Road |
11,200 |
MODERATE |
Perform various flood mitigation at: Mitchell Lnae |
22,000 |
MODERATE |
Erosion at: 1709 Audobon Drive |
3,500 |
LOW |
Stabilize channel at: 221 Scarlett Drive |
750 |
LOW |
Erosion at: 203 Woods Circle |
4,100 |
LOW |
Stabilize channel at: 102 Old Forest Creek |
9,300 |
LOW |
Slip-line pipe at: 913 Roosevelt Drive |
10,450 |
LOW |
TOTAL |
$190,250 |
|