MEMORANDUM

 

TO:                  Mayor and Council

 

FROM:           W. Calvin Horton, Town Manager

 

SUBJECT:      Award of Bid for Bulk Asphalt

 

DATE:            June 26, 2006

 

 

The attached resolution would accept a bid and award a contract to S.T. Wooten Corporation for asphalt and tack coat to be used for street patching by the Public Works Department.  The 2006-2007 budget includes sufficient funds (see below)  for this purchase. 

 

Specifications and bid notices for asphalt and tack coat were distributed to 4 prospective vendors in North Carolina.

 

The Notice to Bidders was published April 5, 2006 on the Town of Chapel Hill’s website.  Two bids were received and opened May 3, 2006, at 3:00 p.m.  The two responsive bids are as follows:

 

ITEM

S.T. Wooten

Riley Paving

 

 

 

Asphalt I-2

$54.00/Ton

$45.00/Ton

 

 

 

Asphalt H

$46.00/Ton

$43.50/Ton

 

 

 

Asphalt HB

$45.00/Ton

$44.00/Ton

 

 

 

Asphalt HDB

$46.00/Ton

$44.00/Ton

 

 

 

Tack Coat (CRS-1)

$3.00/Gal.

$4.00/Gal.

 

 

 

Total

$114,200.00

$106,900.00

 

DISCUSSION

 

The process of patching streets requires that asphalt and tack coat be picked up by Town trucks and delivered to the site when needed.  It is impractical to stockpile the material because it must be applied at high temperatures established at the plant; therefore, we have considered transportation costs in addition to the materials price in analyzing these bids.

 

The year-round availability of hot asphalt is important. The availability of hot-mix asphalt during cold weather allows us to make stable patches when we otherwise would have to use "cold patch," which is unstable.  Potholes receiving cold patch typically disintegrate over the winter, resulting in expensive future repairs.

 

We received two responsive bids from vendors with distances from Chapel Hill noted:  

 

S.T. Wooten Corp.

-16 miles

-28 minutes

 

 

 

Riley Paving Co.

-29miles

-43 minutes

 

Given the estimated 275 mile round trips we make each year and the relative distance of each vendor, we have estimated transportation  costs as follows:

 

 

Vendor

Miles

Time (Hours)

Cost

 

 

 

 

 

 

S.T. Wooten Corp.

8,800

    256

$13,439

 

 

 

 

 

 

Riley Paving Co.

15,950

    394

$22,991

 

The calculation is based on Paragraph 2, entitled "Special Terms and Conditions, of the bid proposal.  In this section, it was stated that travel costs would be calculated and considered as part of the total cost. When the travel costs are calculated, the comparative costs of the two responsive  bids  are as follows:

 

 

Asphalt

Transportation

 

Bidder

Bid

Cost

Total Cost

 

 

 

 

S.T. Wooten Corp.

$114,200

$13,439

$127,639

 

 

 

 

Riley Paving Co.

$106,900

$22,991

$129,891

 

Therefore, we conclude that the total bid of S.T. Wooten Corp. in the amount of $114,200 is the most favorable to the Town.

 

The contract permits an adjustment to the quantity by 25 percent less or more than we estimated.  With this permissible adjustment, the quantities acquired will be adjusted and our actual expenditures would remain within the amount budgeted by the Council. 

 

Option to Extend Contract

 

This contract may be extended by one year if mutually agreeable to both the Town of Chapel Hill and S.T. Wooten Corp. at the same unit prices.  If extended, the contract award would be within approved funding for Fiscal 2007-2008.

 

RECOMMENDATION

 

That the unit prices bid by S.T. Wooten Corp., as stated above, for asphalt and tack coat be accepted by adoption of the attached resolution.