AGENDA #6

 

MEMORANDUM

 

TO:                  Mayor and Town Council

 

From:            W. Calvin Horton, Town Manager

 

Subject:       Concept Plan: Chapel Hill North Proposed Residential Component

 

DATE:             October 20, 2003

 

 

INTRODUCTION

 

Attached for your consideration is a Concept Plan Review.  The proposal involves a request to construct a 190 unit multi-family development on a 12-acre portion of the 40-acre Chapel Hill North development.  The 12-acre site is located on the west side of Perkins Drive, east of the Chapel Hill North Harris Teeter Shopping Center and south of Interstate 40 (I-40).  This Concept Plan is also associated with a separate Concept Plan proposal for the Chapel Hill North Master Land Use Plan approved by the Council in 1990.

 

 

PROCEDURAL BACKGROUND

 

On January 27, 2003, the Council enacted a Land Use Management Ordinance requiring that the Council conduct a Concept Plan Review for proposed developments meeting specific land or floor area thresholds.  Applications (other than in Town Center) meeting any of the minimum thresholds as shown below require Town Council review in addition to Community Design Commission review:

                        Characteristic               Threshold Triggering Council Review

 

                        Land Area                                5 acres

                        Floor Area                               100,000 square feet

                        # of Dwelling Units                   50 dwelling units

 

The Council has the opportunity tonight to hear this applicant’s presentation, receive a set of comments from the Community Design Commission, hear public comment, and offer  suggestions to the applicant for consideration as further plans are drawn.  At the conclusion of the evening’s discussions, we recommend that the Council adopt a resolution (attached) transmitting comments to the applicant.

 

An excerpt from the Land Use Management Ordinance with a description of the process for Concept Plans is attached.


ELEMENTS OF REVIEW

 

A Concept Plan is a preliminary step toward the preparation of a formal development plan and application.  The Land Use Management Ordinance states that design and construction of site elements should include:

 

·        Appropriate descriptions and explanations of the relationship and balance among site elements;

 

·        The relationship of the development to natural features, neighboring developments and undeveloped land;

 

·        Access and circulation systems;

 

·        Retention of natural vegetation, minimal alteration of natural topography, mitigation of erosion and sedimentation, mitigation of stormwater drainage and flooding;

 

·        Arrangement and orientation of buildings and amenities in relation to each other and to neighboring developments and streets;

 

·        Landscaping, preservation or enhancement of vistas; and

 

·        Mitigation of traffic impacts.

 

The Town Council and Community Design Commission, in examining development applications, are to consider the various aspects of design, with special emphasis on whether the proposed development is consistent with the Town’s Design Guidelines and the Goals and Objectives of the Town’s Comprehensive Plan. A work sheet for review of concept plans is included for Council use with this memorandum (Attachment 2).

 

This Concept Plan was reviewed by the Community Design Commission on June 18, 2003.  A summary of comments from that meeting is attached to this memorandum (Attachment 3).

 

BACKGROUND

 

Chapel Hill North Master Land Use Plan- On January 23, 1990, the Town Council approved a Master Land Use Plan for the Chapel Hill North mixed-use development at the intersection of Airport Road and Weaver Dairy Road.  Located in the Mixed-Use Office/Institutional-1 zoning district, the approved plan authorized a total of 633,400 square feet of floor area on the 40-acre site.   The approved Master Land Use Plan specified a mix of uses.

 

Specifically, the approved floor area ratio authorized by the Council with the 1990 Chapel Hill North Master Land Use Plan is:

 

·        Minimum of 374,200 square feet of floor area devoted to office type use (60%);  and

·        Maximum of 259,200 square feet of floor area devoted to retail use (40%).

 

For additional discussion on the mix of uses, refer to the discussion below under Mixed-Use Districts.

 

Chapel Hill North Phase I Special Use Permit- Following approval of the Master Land Use  Plan, the Town Council approved the Phase I Special Use Permit for Chapel Hill North in 1991.  The Phase I approval authorized a portion (102,713 square feet of office type use and 147,807 square feet of retail use) of the floor area approved by the 1990 Master Land Use Plan.

 

MIXED-USE DISTRICTS

 

The Chapel Hill North development is located in the Mixed-Use Office/Institutional-1 (MU-OI-1) zoning district.   This mixed-use zoning district includes special land use intensity standards, specific permitted land use regulations, and development thresholds:

 

The applicant’s proposed Concept Plan for Chapel Hill North proposes to modify the development mix for Chapel Hill North, to reduce office floor area and introduce a residential component.  The MU-OI-1 zone calls out the following development thresholds,

 

 

A.     Minimum lot size of 20 contiguous acres.

 

B.      Uses proposed in one of the following combinations:

 

               * Office, Commercial, and Residential uses

 

               * Office and Commercial uses

 

                *Office and Residential uses.

 

C.     At least 60% of floor area devoted to "business, office-type" uses.

 

D.           No more than 85% of floor area devoted to "business, office-type" uses.

 

 

As proposed the applicant’s Concept Plan would decrease the office ratio threshold (item C above) below the specified 60% minimum.

 

DESCRIPTION OF THE APPLICATION

 

The proposal involves a request to construct a 190 unit multi-family development on a 12 acre portion of the 40 acre Chapel Hill North development.  The proposal includes 240,000 square feet of floor area, 329 parking spaces, and 208,000 square feet of impervious surface area.   The proposed four-story residential buildings include structure parking on the first floor, with residential units on the second, third and fourth floors.  A clubhouse/recreational building and pool are proposed at the southern end of the site.  This Concept Plan application proposes a modification to the Chapel Hill North Special Use Permit.  A comparison between the Master Land Use Plan, the Phase I Special Use Permit and the applicant proposed residential component are outlined in Table #1.

 

  TABLE #1

COMPARISON OF 1990 CHAPEL HILL NORTH MASTER LAND USE PLAN,

 THE 1991 PHASE I SPECIAL USE PERMIT AND THE

RESIDENTIAL COMPONENT PROPOSED BY APPLICANT

 

Master Land Use Plan Approved By Town Council in  1990

1991 Phase I

Special Use Permit

Concept Plan –Residential Component

Total Floor Area

633,400 sq ft

250,500

240,000 sq ft

 

Land Use

(permitted, proposed)

 

Office, Retail (permitted)

 

Office, Retail (permitted)

 

Residential

(proposed)

 

Office  Floor Area

 374,200 sq ft

102,705 sq ft

0 sq ft

Retail Floor Area

259,200 sq ft

147,795 sq ft

0 sq ft

Residential Floor Area

        

  Not permitted

 

Not permitted

240,000 sq ft

(proposed)

 

 

Mixed Use Ratios

 

 

 

Office

 

 

 

 

 

 

Retail

 

 

 

 

 

 

 

Residential

                        

 

1990 Master Land Use Plan

1991 Phase I

 Special Use Permit

Concept Plan Residential Component

 

 

 

60%

 

 

 

41% of the SUP total floor area

 

 

 

0% of Concept Plan

 

36.7% of the total MLUP floor area (based on MLUP Concept Plan proposal)

 

 

40%

 

 

59% of the SUP total floor area

 

0% of Concept Plan)

 

25.4% of the total MLUP floor area (based on MLUP Concept Plan proposal)

 

 

 

0%

 

 

 

0%

100% of Concept Plan

 

37.9 % of the total MLUP floor area (based on Concept Plan proposal)

 

 

The Land Use Plan, a component of the Comprehensive Plan, identifies this site as Mixed-Use Office/Commercial emphasis.  The site is located in the Mixed-Use Office/Institutional-1 (MU-OI-1) zoning district.  The property is within Town Limits and the Town’s Urban Services Area.  This Concept Plan is proposed in the context of the existing zoning for the site.  The tract is located in Orange County and is identified as Chapel Hill Township Tax Map 17, Lot 45.

 

This Concept Plan was reviewed by the Community Design Commission on June 18, 2003.  Community Design Commission Summary is attached to this memorandum (Attachment 2).  We believe that the Concept Plan before the Council tonight is the same plan.

 

RECOMMENDATION

 

We recommend that the Council review this Concept Plan, receive comments from the Community Design Commission and citizens, and adopt a resolution transmitting comments to the applicant. 

 

ATTACHMENTS

 

1.      Excerpt from Land Use Management Ordinance on Concept Plan procedures (p. 7).

2.      Work sheet for concept plan review.  (p. 10).

3.      Community Design Commission Summary Comments June 18, 2003 (p. 12).

4.      Approved Phase I 1991 Special Use Permit (p. 14).

5.      Concept Plan application materials (p.  15).

6.      Area Map (p.  29).

7.      Reduced plans (p. 30).

 

 


A RESOLUTION TRANSMITTING COUNCIL COMMENTS ON A CONCEPT PLAN FOR CHAPEL HILL NORTH RESIDENTIAL COMPONENT (2003-10-20/R-4)

 

WHEREAS, a Concept Plan has been submitted for review by the Council of the Town of Chapel Hill, proposing a residential component  for the Chapel Hill North development; and

 

WHEREAS, the Council has heard presentations from the applicant, the Community Design Commission, and citizens; and

 

WHEREAS, the Council has discussed the proposal, with Council members offering reactions and suggestions;

 

NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Council transmits comments to the applicant regarding this proposal, as expressed by Council members during discussion on October 20, 2003, and reflected in minutes of that meeting.

 

This the 20th day of October, 2003.