FROM: W. Calvin Horton, Town Manager
SUBJECT: Preliminary Report regarding Burial of Town’s Utility/Power Distribution System
DATE:
The purpose of this report is to provide preliminary information on the financial and environmental implications of burying the Town’s electrical power distribution system.
If the Council wishes to pursue action to bury Town electrical facilities, then we recommend waiting until completion of a report on this subject by the N.C. Utilities Commission’s Public Staff.
Attachment 1 provides preliminary information about the implications of burying the Town’s electrical system, including costs involved, environmental impacts, and legislative requirements.
This report provides preliminary information in response
to a January 13 petition from Mr. Joe Capowski, who requested that the Council
initiate a process to bury the electrical power distribution system serving
citizens and businesses in
Mr. Capowski’s petition requests that the Town Council take steps to begin placing the existing electrical distribution system underground, because it is vulnerable to damage by severe weather conditions, as it was during Hurricane Fran and the December 2002 Ice Storm (Attachment 2). The Council has also received petitions from citizens in recent months, requesting that the Council require burial of three-phase power distribution lines associated with new development.
DISCUSSION
According to Mr. Scott Gardner, District
N.C. Utilities Commission
According to Mr.
The Utilities Commission has requested that the
Commission’s Public Staff begin a study to assess the feasibility of burying
overhead electric distribution systems and provide a source document for
responding to continuing inquiries from the general public (Attachment 3). According to Mr.
The Public Staff was created in 1977 to review, investigate, and make recommendations to the Commission regarding utility rates, service, and public policy (Attachment 4).
Duke Energy Policies
According to Mr. Scott Gardner, District
NEXT STEPS
The Public Staff of the Utilities Commission is studying
costs and other issues involved in converting overhead electrical utility
systems to underground. This report is
expected to be complete by
Information on legislation to authorize special taxes to fund the undergrounding of utility lines is contained in the attached report.
We recommend that the Council await the Public Staff’s report on undergrounding of utility lines before taking further action.
The Council was scheduled to meet with the Legislative Delegation on February 17 to discuss items of interest as part of the Town’s Legislative Program. This meeting was canceled because of the ice storm, and a new date has not been set as of this writing.
If the Council wishes to pursue action to bury Town electrical facilities, then we recommend waiting until completion of a report on this subject by the N.C. Utilities Commission’s Public Staff.
We will take further action as directed by the Council.
ATTACHMENTS
1.
Preliminary Report on Implications of Utility/Electrical
System Burial (p. 4).
2.
FROM: Bill Stockard, Assistant to the
Manager
SUBJECT: Preliminary Report on Implications of Utility/Electrical System Burial
DATE:
This attachment
provides further information about the financial, environmental, and
legislative implications involved in possible burial of the Town’s electrical
distribution system.
BACKGROUND AND DISCUSSION
Current Policies
Existing Electrical Facilities
Duke Power Company acquired the electrical power distribution
system from the University on
Pre-2003 Development Ordinance
The pre-2003 Development Ordinance (Section 14.10) required that all utility lines “other than those used to transmit electricity between generating stations or substations and three-phase electric power distribution lines” be placed underground. In response to citizen petitions, the Council asked that the revised Land Use Management Ordinance contain more provisions for burial of three-phase distribution lines.
On
2003 Land Use Management Ordinance
The new Land Use Management Ordinance, enacted on
The new Ordinance (Section 5.12.2) expanded on the pre-2003 Development Ordinance language by requiring burial of three-phase electric power distribution lines if:
· Duke Energy agrees in writing to provide utilities underground;
· there is a “rational nexus” between the impact of a proposed development and the proposed utility requirement;
· the costs of placing utilities underground are roughly proportionate to the impacts of development;
· the development applicant has the legal right to place lines underground where they are located off-site.
The Land Use Management Ordinance does not require burial of three-phase lines if an applicant or Duke Energy demonstrates that the burial would create “economic hardship or a danger to public health or safety.” The Council’s requirements for burial have followed guidelines established by the N.C. Utilities Commission and National Electric Safety Code.
The Council has also expressed interest in legislation from the N.C. General Assembly that would establish a mechanism for burying power distribution lines. We have provided information below under “Legislative Initiatives.”
Conversion Costs
According to information provided by Duke Energy, BellSouth, Verizon, and Time Warner Cable, burial of existing overhead utilities, including electric distribution, telephone, and cable television lines and equipment, would cost more than $500 million, as explained below.
Duke Energy
Power lines are usually buried 36 inches or deeper, telephone lines 24 inches, and cable lines 12 inches.
In estimating the expense of conversion from overhead to underground, Duke Energy’s considerations would include:
· Trenching and burial costs
· Trees that must be removed and possibly replaced
· Potential damage to property and landscaping
· Parking lot or other infrastructure damage
· Moving feeders and cost of service upgrades to businesses
According to the attached Report to the Town of Chapel Hill: Duke Power Underground Facilities, Duke Energy estimates that the costs for an undeveloped area installation can run more than six times the cost to install overhead lines (Attachment 5). In developed areas, conversion costs can be more than 18 times the cost of installing facilities overhead.
Mr. Gardner estimates that conversion costs could be
approximately $2.5 million per mile in
· $500 million over 10 years = $50 million per year
· $50 million per year divided by 21,500 customers = $2,326 per customer per year
· $2,326 per customer per year divided by 12 months = $194 per month for 10 years – in addition to the customer’s existing electric bill.
Mr. Gardner said that the average customer bill is currently between $70 and $80 per month. We recognize that the above preliminary estimates are based on customers paying equally, and that there are other methods of dividing costs between customers.
A survey of 457
Burial of the system would also involve coordination to bury the overhead lines of other utilities, such as telephone and cable.
BellSouth
According to Mr. Ed Penny, Director of Corporate and
External Affairs for BellSouth, there are 1.6 million feet of aerial telephone
cables in
Mr. Penny also said that operation and maintenance costs are often higher for below-ground cables due to delays in locating the failure and special equipment required to expose problem areas. Mr. Penny said that BellSouth experiences more damage to below-ground cables due to digging activities. Because electrical cables are buried more deeply than telephone cables (generally 3 feet for electrical, versus 2 feet below the surface for telephone), telephone facilities are more vulnerable to digging activity than power lines, Mr. Penny said.
According to Mr. Nat
Carpenter of the Public Staff Communications Division of the N.C. Utilities
Commission, the Town could only require a telephone company to bury lines
through a condition imposed for the use of the right-of-way. The Town does not have a franchise agreement
with BellSouth. The Town had a previous
franchise with BellSouth dating back to 1902, but by law, the franchise was
limited to 60 years and expired in 1962.
BellSouth has refused to enter into a new franchise. We believe that the company might refuse to
bury the facilities without compensation.
Verizon
Verizon also provides telephone service to the Town,
mostly the eastern part of town and in
Time Warner
According to Ms.
Town Traffic Signal System
The Town of
Issues to
Consider regarding Burial of Electric Distribution Lines
Weather Exposure
Overhead systems are more exposed to high winds, weather,
wildlife, and several environmental factors that would not affect underground
systems. During snow and ice storms, fallen trees and debris are not as likely
to affect underground systems. According
to Mr. Turner of the Utilities Commission, virtually all electric lines damaged
during the December ice storm were damaged by trees and not directly by
ice. As pointed out in Mr. Capowski’s
petition, there were substantial costs and safety issues involved when nearly
all
Underground systems are vulnerable to damage from flooding or erosion, or accidental severance through unauthorized digging.
Community Appearance
Overhead systems are viewed as unsightly. Community appearance would be improved if power lines were buried, as stated in Mr. Capowski’s petition (Attachment 2).
Costs and Rates
Overhead systems are the standard, “least cost” method for power distribution, as stated by the Utilities Commission. With an underground system, overall utility rates could increase. According to Mr. Turner of the N.C. Utilities Commission, electric rates could more than double if overhead lines are required to be buried.
Maintenance and Reliability
Overhead systems are more easily maintained than underground lines, according to Duke Energy officials. It is more difficult to determine where problem areas are with underground lines because the network is buried (Attachment 5). Mr. Gardner said that once the location of the damage is determined, it takes an average of one hour to repair an overhead line, but it would take an average of four or more hours to repair an underground line.
Environmental Impacts
Overhead systems necessitate the trimming of trees to clear branches away from power lines. The December ice storm renewed discussion about tree-trimming practices in the Town limits. In the past, poles for distribution lines were typically installed in the right-of-way and/or in standard 30-foot-wide utility easements.
Over the last 10 years, Duke Energy has used “directional pruning practices,” a system of selective removal of limbs and branches to minimize conflicts with utility lines. Duke Energy maintains its easements in accordance with the terms of an annual tree work permit originally negotiated with the Town in 1989. This tree work permit includes a requirement that the company notify the Town’s Urban Forester of ongoing easement maintenance work and that it use Town landscaping standards, including directional pruning.
Underground systems would require the removal of some
trees, which may be lost during the trenching process involved in burying lines
(see Attachment 8).
Legislative
Initiatives
We are not likely to be able to force Duke Energy and other utilities to bury overhead lines and pay for the cost from their own profits. If the Council were to pursue burial of electrical or other utility systems, we believe that special enabling legislation would be necessary in order to finance the project. We believe that the funding mechanism could involve formation of a Utility Tax District and/or the creation of a Municipal Service District with a special property tax.
Utility Tax District
Creation of a Utility Tax District would enable the Town
to levy a tax on utility bills to fund the burial of electric utility
lines. The N.C. General Assembly has
authorized this legislation for
The
Special Service District
Creation of a Municipal Service District would enable the Town to levy a special property tax in a given area to fund burial of electric utility lines. Currently, State law allows service district taxes to be levied for burial of utilities only in service districts that are Historic Districts.
Under the current provisions of the N.C. General Statutes, the Town established the Downtown Service District in 1989 to enhance the downtown area. The Downtown Commission provides services funded from the Downtown Service District tax. Similarly, with additional special enabling legislation, the Council could create service districts other than just Historic Districts within the Town for the purpose of funding utility line burial in those districts.
CONCLUSION
If the Council wishes to pursue action to bury Town electrical facilities, then we recommend waiting until completion of a report on this subject by the N.C. Utilities Commission’s Public Staff.