AGENDA #11

MEMORANDUM

 

TO:                  Mayor and Town Council

 

FROM:            W. Calvin Horton, Town Manager

 

SUBJECT:       Recommended 2004 Downtown Improvement Project

 

DATE:             April 14, 2004

 

 

Adoption of the attached resolution would authorize the Town Manager to submit a Specialty Lighting Request to Duke Power Company for the installation of street and pedestrian lighting at two downtown locations where other Streetscape improvements, including the underground duct bank necessary to serve the proposed light fixtures, have already been completed. These locations include the north side of West Franklin Street from Church Street to 306 (formerly Fowlers) and the south side of West Franklin Street adjacent to the University Baptist Church.  The cost of these improvements is estimated to be approximately $95,000.

 

BACKGROUND

 

On November 22, 1993, the Town Council approved the Downtown Streetscape Master Plan. Since that time, construction projects totaling 3,168 linear feet have been completed by Public Works crews.  In addition to improvements constructed by Public Works crews, private developers and Orange County have installed several sections of improvements in conjunction with new construction and the renovation of existing downtown buildings.  A map of the Streetscape study area indicating where improvements have been completed is included in the attachments (Attachment 1).

 

In 1996, $1,000,000 in Streets and Sidewalks bonds were approved for Streetscape improvements.  Of the total $1,000,000, approximately $554,316 has been allocated for construction projects since 1999 and an additional $350,000 has been encumbered for lighting and traffic signal improvements. 

 

The final balance remaining of the 1996 Streets and Sidewalks bond funds is approximately $96,000 which is estimated to be sufficient for completion of the recommended lighting improvements.

 

In November of 2003, a bond referendum was approved by voters that included authorization of $2 million for future Streetscape projects, including lighting.  We anticipate that the initial sale of bonds will generate $500,000 for Streetscape improvements by 2005.  Of that total, approximately $300,000 could be used for lighting and traffic signal improvements in addition to those being proposed to be installed with the available funding.  The approximately $200,000 in remaining funds could be used to construct sidewalk improvements at several locations including one or more of those presented as options in this report and outlined in the attachments.

 

DISCUSSION

 

Each year prior to construction, we have provided the Council with proposals detailing different locations where Streetscape improvements are needed and could be constructed using in-house labor during the summer construction season. This report presents one option that describes installation of custom lighting in sections where Streetscape improvements are already in place, including the underground ductbank necessary to serve the new light fixtures. In addition to this recommended project, four options are provided that involve Streetscape sidewalk reconstruction projects that are each of a size that can be completed using primarily in-house labor between June 1 and August 24, 2004.

 

The attachments include detailed descriptions of each of the five proposals accompanied by summaries of advantages and disadvantages, and cost estimates for each option.  Conceptual plans of the four construction projects presented for consideration are also included (Attachments 3, 4, 5 and 6).

 

Recommended Project – Install custom street and pedestrian lighting improvements in two locations where other Streetscape improvements have previously been completed: 1) the north side of West Franklin Street from Church Street to 306 (formerly Fowlers); and 2) the south side of West Franklin Street in front of the University Baptist Church, at an estimated cost of $95,000.  A detailed description of this project is included in Attachment 2.

 

The two locations recommended for lighting improvements are adjacent to the two downtown locations (the 100 block of East Franklin Street and the Streetscape demonstration project site in the 400 block of West Franklin Street), where lighting improvements have already been installed.  We believe that the installation of lighting improvements at these locations will start to complete a more continuous and uniform pattern of downtown lighting that will not only be an aesthetic improvement but will improve visibility and pedestrian safety in these areas.  Another advantage to the recommended project is that it could be accomplished without utilizing the Public Works Department’s construction crew thereby freeing up this labor resource for use on pending sidewalk construction projects that would otherwise be delayed.

 

Possible Options:  In addition to the above recommended project, the Council could consider other possible projects that would utilize the approximately $96,000 in available funding.  Four alternative projects are presented in this report and include:

 

Option 1 - South side of the 400 block of West Franklin Street from Kenan Street to the west side of Parking Lot #3 (Attachment 3) at an estimated cost of $111,000;

 

Option 2 - South side of the 400 block of West Franklin Street from the former Chrysler dealership (419) to Roberson Street (Attachment 4) at an estimated cost of $94,000; and

 

Option 3 - North side of the 500 and 600 blocks of West Franklin Street from Chapel Hill Tire to Crook’s Corner (Attachment 5) at an estimated cost of $106,000.

 

Option 4 – South side of East Franklin Street from McCorkle Place to Chapel of the Cross (304 East Franklin) at an estimated cost of $100,000 (Attachment 6). This option was included in response to a recent petition to the Council from members of the Chapel of the Cross.  A copy of this petition is included as a part of Attachment 6.  While we think that this project would address some of the goals of the Streetscape Master Plan, we believe that the location is peripheral to the downtown commercial area and that the limited remaining Streetscape funds could be more effectively used to continue downtown lighting improvements at this time.

 

Although several of the alternative projects include cost estimates that slightly exceed the available funding, we believe that minor modifications to each could be developed, such as delaying the installation of some site furnishings, to construct them at this time within the limited budget.  We believe that each of these projects has specific advantages and that they are likely to be undertaken at some point when additional funding is available.

 

RECOMMENDATION

 

We recommend that the Council approve the attached resolution authorizing the Town Manager to submit a Specialty Lighting Request to Duke Power Company for the installation of Phase Two street and pedestrian lighting in two sections of West Franklin Street as indicated on the attached map and to allocate $95,000 of the remaining $96,000 balance of the 1996 Streets and Sidewalks bond for these proposed lighting improvements.

 

ATTACHMENTS

 

1.      Map showing Streetscape construction completed to date (p. 5).

2.      Recommended Project - description of locations for installation of custom street and pedestrian-level lighting (p. 6).

3.      Option 1 – description and preliminary plan for improvements to the south side of the 400 block of West Franklin Street from Kenan Street to the west side of Town Parking Lot #3   (p. 9).

4.      Option 2 – description and preliminary plan for improvements to the south side of the 400 block of West Franklin Street from University Chrysler (419) to Roberson Street (p. 13).

5.      Option 3 – description and preliminary plan for improvements to the north side of the 500 and 600 blocks of West Franklin Street from Chapel Hill Tire (502) to Crook’s Corner (610) (p. 15).

6.      Possible Future Project 4 – description and preliminary plan for improvements to the south side of East Franklin Street from McCorkle Place to Chapel of the Cross (304 East Franklin) (p. 17).


A RESOLUTION AUTHORIZING THE TOWN MANAGER TO REQUEST THAT DUKE POWER COMPANY INSTALL NEW STREET AND PEDESTRIAN LIGHTS IN TWO SECTIONS OF WEST FRANKLIN STREET INDICATED ON THE ATTACHED MAP AND AS SPECIFIED ON THE DOWNTOWN STREETSCAPE LIGHTING PLAN, AND TO UTILIZE $95,000 of THE REMAINING $96,000 BALANCE OF 1996 STREETS AND SIDEWALKS BOND FUNDS FOR These LIGHTING IMPROVEMENTS (2004-04-14/R- 16)

 

WHEREAS, the Council adopted the Downtown Streetscape Master Plan as part of the Town’s Comprehensive Plan; and

 

WHEREAS, lighting improvements are a fundamental part of the Town’s Downtown Streetscape Master Plan; and

 

WHEREAS, $96,000 currently exists in bond funding to implement a portion of the Streetscape Master Plan; and

 

WHEREAS, the Council has received a report from the Town Manager describing a plan for lighting improvements as well as four alternative plans for possible construction by Town labor forces in 2004; and

 

WHEREAS, available Town resources permit implementation of only one of the five options;

 

NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Council authorizes the Town Manager to submit a Specialty Lighting Request to Duke Power Company for the installation of Phase Two street and pedestrian lighting in two sections of West Franklin Street as indicated on the attached map, and to allocate $95,000 of the remaining $96,000 balance of the 1996 Streets and Sidewalks bond funds for these proposed lighting improvements.

 

This the 14th day of April, 2004.